Question 325 of 1,731
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the Project Manager. This is correct because in PRINCE2, the Project Manager is explicitly responsible for producing and maintaining the Project Plan, which defines the stages, activities, dependencies, and resource estimates, and must ensure it aligns with the Business Case. On the PRINCE2 Foundation exam, this tests your understanding of role-specific accountabilities within the planning theme, and a common trap is confusing the Project Manager’s ownership of the plan with the Project Board’s approval authority—the Board authorizes, but the Manager creates and updates. To remember this, think of the Project Manager as the "plan owner" who drives the planning process from start to finish, while the Board simply signs off. A useful memory tip is the mnemonic "PM Plans, Board Approves," reinforcing that the Project Manager holds the pen for the Project Plan responsibility in PRINCE2.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which role is responsible for the Project Plan?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The Project Manager is responsible for producing and maintaining the Project Plan, as defined in PRINCE2's management products. This includes defining the project's stages, activities, dependencies, and resource estimates, and ensuring the plan aligns with the Business Case. The Project Manager owns the planning process and is accountable for the plan's accuracy and updates throughout the project.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Executive

    Why it's wrong here

    The Executive owns the Business Case, not the plan.

  • Project Board

    Why it's wrong here

    The Project Board approves the plan, but does not create it.

  • Senior User

    Why it's wrong here

    The Senior User provides requirements but does not own the plan.

  • Project Manager

    Why this is correct

    The PM is responsible for planning.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between responsibility for creating versus approving a plan, leading candidates to mistakenly select the Project Board (Option B) because they confuse approval authority with ownership.

Detailed technical explanation

How to think about this question

The Project Plan is a PRINCE2 management product that provides a high-level view of the entire project, including stages, milestones, and resource requirements. It is created during the Initiating a Project process and is updated at the end of each stage. The Project Manager uses techniques like product-based planning to break down deliverables and dependencies, ensuring the plan is realistic and aligned with the project's tolerances.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Project Manager — The Project Manager is responsible for producing and maintaining the Project Plan, as defined in PRINCE2's management products. This includes defining the project's stages, activities, dependencies, and resource estimates, and ensuring the plan aligns with the Business Case. The Project Manager owns the planning process and is accountable for the plan's accuracy and updates throughout the project.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.