Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

⚠ Common exam trap

Test-takers frequently confuse the Project Board's strategic decision-making responsibilities with the Project Manager's operational tasks, such as managing daily work or producing plans, leading them to incorrectly select options D or E.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorize the closure of the project

The Project Board is responsible for making key decisions and exercising overall control over the project. Authorizing closure (A) ensures the project has met its objectives and that the product has been accepted before formal closure. Authorizing an Exception Plan (B) is a board-level decision to approve a deviation from the plan when a tolerance is forecast to be exceeded. Authorizing initiation (C) gives the go-ahead for the project to proceed from the initiation stage into the detailed planning and delivery stages.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Authorize the closure of the project

    Why this is correct

    The Project Board authorizes closure in DP.

  • Authorize an Exception Plan

    Why this is correct

    The Project Board authorizes Exception Plans when tolerances are exceeded.

  • Authorize the initiation of the project

    Why this is correct

    The Project Board authorizes initiation in DP.

  • Manage day-to-day work of the team

    Why it's wrong here

    Day-to-day management is done by the Project Manager in CS.

  • Produce the Project Plan

    Why it's wrong here

    The Project Plan is produced by the Project Manager in IP.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

hard
  • A.Managing risks on a daily basis
  • B.Authorizing initiation of the project
  • C.Preparing Highlight Reports
  • D.Giving ad-hoc direction to the Project Manager
  • E.Authorizing the project closure

Why B: The Project Board is responsible for authorizing the initiation of the project during the Directing a Project process. This authorization formally allows the Project Manager to proceed with the Initiation Stage, committing resources and funding. It is a key decision point that ensures the project aligns with corporate or programme strategy before detailed planning begins.

Variation 2. Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

medium
  • A.Approving stage plans and updates
  • B.Producing Checkpoint Reports
  • C.Managing the day-to-day activities of the project team
  • D.Authorising closure of the project
  • E.Authorising initiation of the project

Why A: The Project Board is responsible for approving Stage Plans and any updates to them during the Directing a Project process. This ensures that the project remains aligned with the business case and that management stage boundaries are properly controlled.

Variation 3. Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?

medium
  • A.Authorize stage plans and give ad-hoc direction
  • B.Produce Checkpoint Reports
  • C.Manage day-to-day activities of the project
  • D.Authorize the initiation of the project
  • E.Update the Business Case

Why A: The Project Board authorizes initiation, authorizes the project, authorizes stage plans, gives ad-hoc direction, and authorizes closure. They do not manage day-to-day work or produce Checkpoint Reports.

Variation 4. Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?

hard
  • A.Authorising project closure
  • B.Managing the Business Case on a day-to-day basis
  • C.Authorising project initiation
  • D.Preparing the Highlight Report
  • E.Appointing the Team Manager

Why A: The Project Board is responsible for authorizing project closure as part of the Directing a Project process. This ensures that the project formally ends only after all objectives have been met, products accepted, and lessons recorded, providing governance and control over the project's lifecycle.

Variation 5. In the Directing a Project process, which of the following is a key responsibility of the Project Board?

easy
  • A.Producing Highlight Reports
  • B.Authorizing the next Stage Plan
  • C.Managing day-to-day work within a stage
  • D.Accepting Work Packages

Why B: In PRINCE2, the Directing a Project process is the decision-making layer where the Project Board exercises overall control. A key responsibility is authorizing the next Stage Plan, which formally approves the detailed plan for the upcoming management stage and commits the resources required to execute it. This ensures the project remains viable and aligned with business justification before proceeding.

Variation 6. Which THREE of the following are responsibilities of the Project Board in the Directing a Project process?

hard
  • A.Producing Highlight Reports
  • B.Giving ad-hoc direction to the Project Manager
  • C.Authorizing the initiation of the project
  • D.Authorizing the closure of the project
  • E.Managing day-to-day work of the project

Why B: The Project Board is responsible for providing overall direction and control of the project. Giving ad-hoc direction to the Project Manager (Option B) is a key responsibility within the Directing a Project process, as the Board must intervene when necessary to keep the project aligned with business objectives.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.