PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are activities performed during the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorize closure of the project
Directing a Project includes authorizing initiation, authorizing stages, giving ad-hoc direction, and authorizing closure. Producing Highlight Reports is for the PM during Controlling a Stage. Appointing the Project Manager is during Starting Up a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Authorize closure of the project
Why this is correct
The Project Board authorizes closure during Directing a Project.
- ✗
Appoint the Project Manager
Why it's wrong here
The Project Manager is appointed during Starting Up a Project.
- ✓
Authorize initiation
Why this is correct
The Project Board authorizes initiation during Directing a Project.
- ✓
Give ad-hoc direction to the Project Manager
Why this is correct
The Project Board provides ad-hoc direction as needed.
- ✗
Produce Highlight Reports
Why it's wrong here
Highlight Reports are produced by the Project Manager during Controlling a Stage.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.