Which process is triggered when the Project Board authorizes a stage plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
When the Project Board authorizes a stage plan, the next process to execute is Controlling a Stage, where the Project Manager manages the work of that stage.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Starting Up a Project
Why it's wrong here
This occurs before any stage authorization.
- ✗
Managing a Stage Boundary
Why it's wrong here
This process produces the stage plan but is executed before authorization.
- ✗
Initiating a Project
Why it's wrong here
This occurs only once, before the first stage.
- ✓
Controlling a Stage
Why this is correct
After a stage plan is authorized, the PM begins controlling that stage.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.