Which process is triggered when the Project Board authorizes a stage plan?

⚠ Common exam trap

PRINCE2F often tests the boundary between Managing a Stage Boundary and Controlling a Stage — candidates confuse the process that seeks authorization with the process that executes the authorized stage, picking Managing a Stage Boundary when the question asks what is triggered after authorization.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

In PRINCE2, when the Project Board authorizes a stage plan at a stage boundary, the next stage begins and the 'Controlling a Stage' process is triggered to manage the day-to-day work of that authorized stage. Managing a Stage Boundary is the process that produces the plan and seeks authorization; Controlling a Stage is what runs once authorization is granted.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Starting Up a Project

    Why it's wrong here

    Starting Up a Project precedes the project mandate and appoints the executive and project manager; it cannot be triggered by stage authorisation, which occurs mid-project. It is tempting because it also handles authorisation of the project itself, and it would be correct when responding to a new project mandate.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Authorising a stage plan happens within Directing a Project, where the Project Board approves the next stage; Managing a Stage Boundary produces that plan and is triggered by the current stage's approaching end, not by board authorisation. It is tempting because it does create and update the stage plan the board then reviews.

  • ✗

    Initiating a Project

    Why it's wrong here

    Initiating a Project produces the project initiation documentation and is triggered by the project mandate, before any stage plan exists to authorise. It is tempting because it also involves Project Board approval, and it would be correct when the board authorises the project brief and PID.

  • ✓

    Controlling a Stage

    Why this is correct

    Controlling a Stage begins once the Project Board authorises the next stage plan, satisfying the trigger condition in the stem. The Project Manager then authorises work packages, monitors progress and manages issues and risks within that stage, reporting via Highlight Reports until the stage completes.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.