Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorise initiation of the project

The Project Board authorises initiation, stage plans, and project closure. They do not create Work Packages (PM does) nor approve Checkpoint Reports (PM receives them).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Create Work Packages

    Why it's wrong here

    PM creates Work Packages in CS.

  • Authorise initiation of the project

    Why this is correct

    Project Board authorises initiation.

  • Approve Checkpoint Reports

    Why it's wrong here

    PM receives Checkpoint Reports; Project Board receives Highlight Reports.

  • Authorise project closure

    Why this is correct

    Project Board authorises closure.

  • Authorise a Stage Plan

    Why this is correct

    Project Board authorises stage plans.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.