PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorise initiation of the project
The Project Board authorises initiation, stage plans, and project closure. They do not create Work Packages (PM does) nor approve Checkpoint Reports (PM receives them).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Create Work Packages
Why it's wrong here
PM creates Work Packages in CS.
- ✓
Authorise initiation of the project
Why this is correct
Project Board authorises initiation.
- ✗
Approve Checkpoint Reports
Why it's wrong here
PM receives Checkpoint Reports; Project Board receives Highlight Reports.
- ✓
Authorise project closure
Why this is correct
Project Board authorises closure.
- ✓
Authorise a Stage Plan
Why this is correct
Project Board authorises stage plans.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.