PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are activities performed during the Managing a Stage Boundary process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Produce a Stage Plan for the next stage
In SB, the PM produces the End Stage Report, updates the Project Plan, and produces a Stage Plan for the next stage. Authorizing work packages is done in CS. Producing Highlight Reports is done in CS.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Produce a Stage Plan for the next stage
Why this is correct
Correct. The next stage plan is produced in SB.
- ✗
Produce a Highlight Report
Why it's wrong here
Highlight Reports are produced in Controlling a Stage.
- ✓
Produce the End Stage Report
Why this is correct
Correct. The End Stage Report is produced in SB.
- ✓
Update the Project Plan
Why this is correct
Correct. The Project Plan is updated to reflect progress and plans.
- ✗
Authorize work packages
Why it's wrong here
Authorizing work packages happens in Controlling a Stage.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.