Which THREE of the following are activities performed during the Managing a Stage Boundary process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Produce a Stage Plan for the next stage

In PRINCE2, the Managing a Stage Boundary process prepares the next stage and reports on the current one, so option A (Produce a Stage Plan for the next stage) is correct because the next Stage Plan is created here for the project board to approve. Option C (Produce the End Stage Report) is correct because this report summarizes the ending stage's performance and is a required output used by the board to decide whether to continue. Option D (Update the Project Plan) is correct because the Project Plan is updated with actuals and the approved next-stage information to keep the overall plan current. Option B (Produce a Highlight Report) is not part of this process; Highlight Reports are produced during Controlling a Stage. Option E (Authorize work packages) is also not part of this process; work packages are authorized in Controlling a Stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Produce a Stage Plan for the next stage

    Why this is correct

    Managing a Stage Boundary requires producing a Stage Plan for the next stage, covering products, activities, tolerances and resources. The Project Board reviews this plan alongside the End Stage Report to decide whether to authorise the following stage.

  • ✗

    Produce a Highlight Report

    Why it's wrong here

    Highlight Reports are produced during Controlling a Stage, giving the board a regular progress summary within the stage. Managing a Stage Boundary instead produces the End Stage Report and next Stage Plan, so a Highlight Report is not one of its activities.

  • ✓

    Produce the End Stage Report

    Why this is correct

    Managing a Stage Boundary requires producing the End Stage Report, reviewing performance of the closing stage against its Stage Plan and Business Case. It accompanies the next Stage Plan for Project Board approval at the end-stage assessment.

  • ✓

    Update the Project Plan

    Why this is correct

    Updating the Project Plan is a Managing a Stage Boundary activity, since the plan must be revised to reflect actual progress and the next stage's forecast before the End Stage Report and next Stage Plan are submitted to the Project Board for approval.

  • ✗

    Authorize work packages

    Why it's wrong here

    Authorising work packages occurs in Controlling a Stage, where the Project Manager approves and issues them to Team Managers. Managing a Stage Boundary instead covers producing the End Stage Report, updating the Project Plan and preparing the next Stage Plan for the board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.