A project is forecast to exceed its cost tolerance at stage level. What should the Project Manager do first?

⚠ Common exam trap

Watch out — candidates often confuse the Project Manager's authority to manage day-to-day issues with the need to escalate tolerance breaches, leading them to incorrectly choose Option A (increasing the budget) or Option D (delaying escalation).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

In PRINCE2, when a project forecasts exceeding its stage-level cost tolerance, the Project Manager must first escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager does not have authority to exceed the delegated tolerance; the Project Board must decide on corrective action, such as approving a revised plan or closing the project. Option C is correct as it aligns with the PRINCE2 principle of management by exception.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Increase the stage budget and continue

    Why it's wrong here

    Incorrect. The Project Manager does not have the authority to increase the stage budget; exceeding tolerance requires escalation.

  • Close the project as the Business Case is not viable

    Why it's wrong here

    Incorrect. Closing the project is a decision for the Project Board, not the first action of the Project Manager when tolerance is forecast to be exceeded.

  • Raise an Exception Report to the Project Board

    Why this is correct

    Correct. An Exception Report is raised to inform the Project Board of the forecast deviation and seek their direction.

  • Wait until the next Highlight Report

    Why it's wrong here

    Incorrect. Waiting for the next Highlight Report delays escalation; the Project Manager should immediately raise an Exception Report.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.