Drag steps to the numbered slots on the right, or tap a step then tap a slot.
PRINCE2F Business Case and Organizing Practice Question
Drag and drop the steps to manage a product delivery work package in PRINCE2 into the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Accept the Work Package, then Execute the Work Package, then Deliver the Products, then Obtain Approval for the Products, then Report Completion
Managing Product Delivery involves accepting the work package, executing the work, delivering the products, obtaining approval, and then reporting completion.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Accept the Work Package, then Execute the Work Package, then Deliver the Products, then Obtain Approval for the Products, then Report Completion
Why this is correct
This is the correct sequence because in PRINCE2, the team manager first accepts the work package from the project manager, then executes the work to create the products, delivers the completed products, obtains formal approval from the project manager, and finally reports completion of the work package.
- ✗
Execute the Work Package, then Accept the Work Package, then Deliver the Products, then Obtain Approval for the Products, then Report Completion
Why it's wrong here
This order is incorrect because the work package must be accepted before execution can begin. Accepting the work package authorizes the team to start work; executing without acceptance violates PRINCE2's authorization principle.
- ✗
Accept the Work Package, then Execute the Work Package, then Obtain Approval for the Products, then Deliver the Products, then Report Completion
Why it's wrong here
This order is incorrect because approval of the products should occur after they are delivered, not before. The project manager needs to review the delivered products before granting formal approval.
- ✗
Accept the Work Package, then Deliver the Products, then Execute the Work Package, then Obtain Approval for the Products, then Report Completion
Why it's wrong here
This order is incorrect because products cannot be delivered before they are created. Execution must precede delivery; otherwise, there would be nothing to deliver.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.