Drag and drop the steps of the PRINCE2 Controlling a Stage process into the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Authorize Work Packages, then Review Work Package Status, then Receive Completed Work Packages, then Review Stage Status, then Report Highlights, then Capture and Examine Issues and Risks, then Take Corrective Action, then Escalate Issues and Risks (if needed)
Controlling a Stage includes authorizing work, reviewing progress, assessing stage status, reporting to the Project Board, and taking corrective action as needed.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Authorize Work Packages, then Review Work Package Status, then Receive Completed Work Packages, then Review Stage Status, then Report Highlights, then Capture and Examine Issues and Risks, then Take Corrective Action, then Escalate Issues and Risks (if needed)
Why this is correct
This is the correct order as per PRINCE2: first authorize work, then monitor progress, review status, report, and handle issues with corrective action and escalation if necessary.
- ✗
Report Highlights, then Authorize Work Packages, then Review Work Package Status, then Receive Completed Work Packages, then Review Stage Status, then Capture and Examine Issues and Risks, then Take Corrective Action, then Escalate Issues and Risks (if needed)
Why it's wrong here
This is incorrect because reporting highlights should occur after reviewing stage status, not before authorizing work.
- ✗
Take Corrective Action, then Authorize Work Packages, then Review Work Package Status, then Receive Completed Work Packages, then Review Stage Status, then Report Highlights, then Capture and Examine Issues and Risks, then Escalate Issues and Risks (if needed)
Why it's wrong here
This is incorrect because corrective action must be based on identified issues and risks, which come after reviewing status and capturing issues.
- ✗
Escalate Issues and Risks (if needed), then Authorize Work Packages, then Review Work Package Status, then Receive Completed Work Packages, then Review Stage Status, then Report Highlights, then Capture and Examine Issues and Risks, then Take Corrective Action
Why it's wrong here
This is incorrect because escalation is a last resort after attempting corrective action, not the first step.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.