PRINCE2F PRINCE2 Processes Practice Question
The Project Board is considering a request to close a project early due to loss of business justification. Which process is the Project Board using to make this decision?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
The Project Board uses the Directing a Project process throughout the project, including authorising closure. Closing a Project is the process that produces the recommendation, but the decision to close is taken by the Project Board via Directing a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing a Stage Boundary
Why it's wrong here
This process occurs at the end of each stage, not for premature closure.
- ✗
Closing a Project
Why it's wrong here
Closing a Project is the process that prepares the closure recommendation; the decision to close is made by the Project Board in Directing a Project.
- ✗
Starting Up a Project
Why it's wrong here
SU is pre-project; not relevant here.
- ✓
Directing a Project
Why this is correct
Correct. DP includes the activity 'Authorise Project Closure'.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.