PRINCE2F PRINCE2 Practices Practice Question
During a stage, a team manager discovers a product cannot be delivered on time due to technical issues. The stage plan has no tolerance left for time. What should the team manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Inform the Project Manager via a Checkpoint Report
When a work package tolerance is forecast to be exceeded, the team manager should inform the Project Manager via a Checkpoint Report so the PM can assess impact.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Inform the Project Manager via a Checkpoint Report
Why this is correct
Correct. The team manager reports to the PM, who then decides on escalation.
- ✗
Raise an Exception Report directly to the Project Board
Why it's wrong here
The team manager does not escalate directly to the Board; they report to the PM.
- ✗
Continue working and catch up later
Why it's wrong here
Ignoring tolerance breach is not acceptable.
- ✗
Request more time from the Senior User
Why it's wrong here
The team manager should not bypass the PM.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.