Courseiva
PRINCE2 PracticeseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which document is used to capture and track all identified risks throughout the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk Register

The Risk Register is the document used to record and track risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Quality Register

    Why it's wrong here

    The Quality Register records quality activities and results.

  • Risk Register

    Why this is correct

    The Risk Register captures and tracks all risks.

  • Configuration Item Record

    Why it's wrong here

    Configuration Item Records track product versions, not risks.

  • Issue Register

    Why it's wrong here

    The Issue Register records issues, not risks.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.