Which document is used to capture and track all identified risks throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk Register
The Risk Register is the document used to record and track risks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Quality Register
Why it's wrong here
The Quality Register records quality activities and results.
- ✓
Risk Register
Why this is correct
The Risk Register captures and tracks all risks.
- ✗
Configuration Item Record
Why it's wrong here
Configuration Item Records track product versions, not risks.
- ✗
Issue Register
Why it's wrong here
The Issue Register records issues, not risks.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.