PRINCE2F PRINCE2 Practices Practice Question
Which role is responsible for ensuring that project assurance is carried out independently of the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Project Board members (Executive, Senior User, Senior Supplier) are responsible for project assurance. They delegate assurance tasks but remain accountable. The Project Manager does not perform assurance; that would compromise independence.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The Project Manager is responsible for day-to-day management, not independent assurance.
- ✓
Project Board
Why this is correct
Correct. The Project Board is accountable for project assurance and ensures it is independent.
- ✗
Team Manager
Why it's wrong here
Team Managers deliver products; they are not responsible for independent assurance.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative help, not assurance.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.