PRINCE2F PRINCE2 Practices Practice Question
What is the purpose of the Highlight Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To report progress to the Project Board at regular intervals
The Highlight Report is produced by the Project Manager for the Project Board at regular intervals to summarize progress and issues.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To escalate exceptions
Why it's wrong here
Exception Reports escalate exceptions.
- ✓
To report progress to the Project Board at regular intervals
Why this is correct
Correct.
- ✗
To request changes
Why it's wrong here
Change requests are separate.
- ✗
To report progress to the Team Manager
Why it's wrong here
Team Managers receive Checkpoint Reports.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.