Who is responsible for maintaining the Business Case throughout the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Manager

The Executive (Senior Responsible Owner) is the owner of the Business Case. The Project Manager maintains (updates) the Business Case on behalf of the Executive.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Senior User

    Why it's wrong here

    The Senior User represents the users and is not responsible for maintaining the Business Case.

  • The Project Assurance

    Why it's wrong here

    Project Assurance provides independent oversight, not maintenance of the Business Case.

  • The Project Manager

    Why this is correct

    The Project Manager maintains the Business Case on behalf of the Executive.

  • The Senior Supplier

    Why it's wrong here

    The Senior Supplier provides supplier resources and is not responsible for maintaining the Business Case.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.