Question 936 of 1,731
PRINCE2 ProcessesmediumMultiple SelectObjective-mapped

Quick Answer

The answer is that the Project Board is responsible for authorizing the start of each stage. This is correct because the Project Board provides overall project governance, ensuring that each management stage begins only after a formal review of the previous stage’s results and a re-evaluation of the business justification. In PRINCE2, the Board does not manage day-to-day work; instead, it makes key decisions at stage boundaries to maintain control over the project’s viability. On the PRINCE2 Foundation exam, this concept tests your understanding of the Board’s strategic role versus the Project Manager’s tactical role, and a common trap is confusing the Board’s authorization of stage starts with the Project Manager’s responsibility for producing stage plans. To remember this, think of the Board as the “gatekeeper” at each stage boundary—they hold the keys to let the next stage proceed.

PRINCE2F PRINCE2 Processes Practice Question

This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are responsibilities of the Project Board?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorize the Project Plan

The Project Board is responsible for overall project governance, including authorizing the Project Plan (which defines the project's scope, cost, and schedule) and authorizing the start of each management stage. These decisions ensure the project remains aligned with business objectives and that stage boundaries are properly controlled.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Manage day-to-day activities

    Why it's wrong here

    Done by PM in CS.

  • Authorize the Project Plan

    Why this is correct

    The board approves the Project Plan.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Produce Checkpoint Reports

    Why it's wrong here

    Done by Team Manager in MP.

  • Authorize the start of each stage

    Why this is correct

    Done in DP.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Update the Daily Log

    Why it's wrong here

    Updated by PM.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between strategic governance (Project Board) and operational management (Project Manager), so candidates mistakenly assign day-to-day tasks like updating logs or producing reports to the board.

Detailed technical explanation

How to think about this question

In PRINCE2, the Project Board's authority is exercised through formal authorizations at key decision points: the initiation stage (authorizing the Project Plan) and at each stage boundary (authorizing the next stage). This ensures that the board retains control over major commitments of resources and that the project does not proceed without explicit approval, even if the Project Manager has day-to-day control.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Authorize the Project Plan — The Project Board is responsible for overall project governance, including authorizing the Project Plan (which defines the project's scope, cost, and schedule) and authorizing the start of each management stage. These decisions ensure the project remains aligned with business objectives and that stage boundaries are properly controlled.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.