Courseiva
People: organizations, teams, and leadershipmediumMultiple SelectObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

Which TWO roles are part of the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior User

The Project Board consists of three roles: the Executive (Senior Responsible Owner), Senior User(s), and Senior Supplier(s). In this question, the two roles from the Project Board that are listed are Senior User (Option A) and Executive (Option E). Team Manager, Project Manager, and Project Support are not Project Board roles.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior User

    Why this is correct

    The Senior User is a board role.

  • Team Manager

    Why it's wrong here

    The Team Manager is not on the board.

  • Project Manager

    Why it's wrong here

    The PM is not on the board.

  • Project Support

    Why it's wrong here

    Project Support is not on the board.

  • Executive (SRO)

    Why this is correct

    The Executive is a board role.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.