PRINCE2F People: organizations, teams, and leadership Practice Question
Which TWO roles are part of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior User
The Project Board consists of three roles: the Executive (Senior Responsible Owner), Senior User(s), and Senior Supplier(s). In this question, the two roles from the Project Board that are listed are Senior User (Option A) and Executive (Option E). Team Manager, Project Manager, and Project Support are not Project Board roles.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Senior User
Why this is correct
The Senior User is a board role.
- ✗
Team Manager
Why it's wrong here
The Team Manager is not on the board.
- ✗
Project Manager
Why it's wrong here
The PM is not on the board.
- ✗
Project Support
Why it's wrong here
Project Support is not on the board.
- ✓
Executive (SRO)
Why this is correct
The Executive is a board role.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.