Which TWO roles are part of the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Senior User

The Project Board consists of three roles: the Executive (Senior Responsible Owner), Senior User(s), and Senior Supplier(s). In this question, the two roles from the Project Board that are listed are Senior User (Option A) and Executive (Option E). Team Manager, Project Manager, and Project Support are not Project Board roles.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Senior User

    Why this is correct

    The Senior User represents those who will use the project's products and confirms they meet requirements, making it one of the three Project Board roles alongside Executive and Senior Supplier. This satisfies the stem's requirement for roles constituting the Project Board.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager manages delivery of products assigned by the Project Manager and reports to that role, not to the Project Board. It is tempting because Team Managers attend checkpoint and quality reviews, but PRINCE2 places them below the Project Manager in the delivery layer, holding no Board-level accountability.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day on the Board's behalf and reports to it, rather than sitting on it. It is tempting because the Project Manager attends every Board meeting and supplies progress information, but PRINCE2 defines the Board as Executive, Senior User and Senior Supplier only.

  • ✗

    Project Support

    Why it's wrong here

    Project Support is an administrative role that advises and assists the Project Manager, sitting outside the Project Board's three roles of Executive, Senior User and Senior Supplier. It is tempting because Project Support reports to the Board and attends meetings, but it holds no decision-making accountability or ownership of a business, user or supplier interest.

  • ✓

    Executive (SRO)

    Why this is correct

    The Executive, often filled by the Senior Responsible Owner, owns the business case and holds ultimate accountability for the project. This satisfies the stem's requirement for Project Board membership, sitting alongside the Senior User and Senior Supplier roles.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.