PRINCE2F PRINCE2 Practices Practice Question
During which process are team plans typically created?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Managing Product Delivery
Team plans are created by the team manager during the Managing Product Delivery process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing a Stage Boundary
Why it's wrong here
Stage plans are created here.
- ✗
Initiating a Project
Why it's wrong here
The Project Plan is created here.
- ✗
Directing a Project
Why it's wrong here
This is a Project Board process.
- ✓
Managing Product Delivery
Why this is correct
Correct. Team plans are created by the team manager in MP.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.