A team member reports that a product does not meet its specification. How should the Project Manager record this?

⚠ Common exam trap

Candidates often mistake an Off-specification for a Request for Change. An Off-specification is recorded when an existing product fails to meet its agreed specification, whereas a Request for Change proposes a modification to the specification. This question tests the correct classification of issues in PRINCE2.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

As an Off-specification

In PRINCE2, an Off-specification is the correct record when a product fails to meet its agreed specification or quality criteria. The Project Manager logs this in the Issue Register as a type of issue, not a risk, change, or lesson, because the product already exists and does not conform to its defined requirements.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    As a Risk

    Why it's wrong here

    A specification breach is an actual non-conformance, so PRINCE2 records it as an Issue or Off-Specification, not a Risk, which covers uncertain future events. Risk registration tempts when the breach's consequences are still unknown, but the trigger has already occurred.

  • ✗

    As a Request for Change

    Why it's wrong here

    An Off-Specification is raised as an Issue, not automatically as a Request for Change, because the Project Board must first decide whether to change the specification, accept a concession, or reject the product. An RFC suits a deliberate change to baselined requirements.

  • ✗

    As a Lesson

    Why it's wrong here

    A Lesson captures knowledge for future projects, whereas a current specification breach needs immediate Issue handling and a Project Board decision. Recording it as a Lesson tempts because the root cause may later inform the Lessons Log, but that is retrospective, not the response mechanism.

  • ✓

    As an Off-specification

    Why this is correct

    An Off-specification records a product that fails to meet its agreed specification, capturing the discrepancy for the Project Manager to resolve via change control or tolerance decisions. It is the defined PRINCE2 mechanism for this exact event, distinct from a general issue or a Request for Change.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.