PRINCE2F People: organizations, teams, and leadership Practice Question
Which PRINCE2 principle ensures that the Project Board delegates decision-making to the Project Manager within defined tolerances?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Management by Exception
Management by Exception means the PM is empowered within tolerances, and only escalates when tolerances are forecast to be exceeded.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Learn from Experience
Why it's wrong here
This principle is about lessons learned.
- ✗
Continued Business Justification
Why it's wrong here
This principle focuses on the business case.
- ✓
Management by Exception
Why this is correct
This principle defines tolerance-based delegation.
- ✗
Manage by Stages
Why it's wrong here
This principle is about planning in stages.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.