People: organizations, teams, and leadershipeasyMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

Which role is responsible for maintaining the Business Case throughout the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior Responsible Owner (Executive)

The Senior Responsible Owner (SRO/Executive) owns the Business Case and is accountable for ensuring it remains viable. The Project Manager maintains the Business Case on behalf of the Executive.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Responsible Owner (Executive)

    Why this is correct

    The SRO/Executive is accountable for the Business Case.

  • Project Assurance

    Why it's wrong here

    Project Assurance independently assesses the project but does not maintain the Business Case.

  • Project Manager

    Why it's wrong here

    The Project Manager maintains the Business Case but does not own it.

  • Senior User

    Why it's wrong here

    The Senior User represents user interests but does not own the Business Case.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.