Which role is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior Responsible Owner (Executive)
The Senior Responsible Owner (SRO/Executive) owns the Business Case and is accountable for ensuring it remains viable. The Project Manager maintains the Business Case on behalf of the Executive.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Senior Responsible Owner (Executive)
Why this is correct
The SRO/Executive is accountable for the Business Case.
- ✗
Project Assurance
Why it's wrong here
Project Assurance independently assesses the project but does not maintain the Business Case.
- ✗
Project Manager
Why it's wrong here
The Project Manager maintains the Business Case but does not own it.
- ✗
Senior User
Why it's wrong here
The Senior User represents user interests but does not own the Business Case.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.