Business Case and OrganizinghardMultiple ChoiceObjective-mapped

PRINCE2F Business Case and Organizing Practice Question

During a project, the cost-benefit ratio becomes unfavorable. What is the first action the project manager should take?

⚠ Common exam trap

PeopleCert often tests the misconception that the project manager can independently adjust the Business Case or stop the project, when in fact the project board holds the authority for such decisions under PRINCE2's management by exception and continued business justification principles.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request a formal review of the Business Case by the project board

In PRINCE2, the Business Case is the key document for justifying the project's continued viability. When the cost-benefit ratio becomes unfavorable, the project manager must escalate this issue to the project board, which holds the authority to approve changes to the Business Case or decide on project continuation. Option D is correct because the project manager's first action is to request a formal review by the project board, as per the 'continued business justification' principle and the 'manage by stages' theme.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Business Case without informing the board

    Why it's wrong here

    The board must be informed and approve changes.

  • Reduce project scope to cut costs

    Why it's wrong here

    Scope changes need board approval.

  • Stop the project immediately

    Why it's wrong here

    The project manager must escalate, not stop unilaterally.

  • Request a formal review of the Business Case by the project board

    Why this is correct

    Correct: escalate for board decision.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.