Courseiva
Project Initiation and StageshardMultiple SelectObjective-mapped

PRINCE2F Project Initiation and Stages Practice Question

Which TWO are true about Stage Plans in PRINCE2?

⚠ Common exam trap

Many candidates confuse the level of detail between Stage Plans and the Project Plan; candidates often assume Stage Plans are less detailed because they cover a shorter time period, but PRINCE2 requires them to be more detailed to enable day-to-day management.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

They are approved by the Project Board

Stage Plans in PRINCE2 are formally approved by the Project Board at the end of the current stage (or at the start of the next stage) as part of the 'Manage a Stage Boundary' process. The Project Board uses the Stage Plan to authorize the work for the upcoming stage, ensuring it aligns with the Business Case and tolerances.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • They are approved by the Project Board

    Why this is correct

    The Board approves each Stage Plan.

  • They cover the entire project timeline

    Why it's wrong here

    Stage Plans cover only one stage.

  • They are produced at the start of each stage

    Why this is correct

    Stage Plans are prepared before each stage begins.

  • They replace the Project Plan

    Why it's wrong here

    The Project Plan remains; Stage Plans are complementary.

  • They are less detailed than the Project Plan

    Why it's wrong here

    Stage Plans are more detailed than the Project Plan.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. The project board asks the project manager to produce a detailed plan for the next stage. Which plan should be produced?

medium
  • A.Exception Plan
  • B.Stage Plan
  • C.Team Plan
  • D.Project Plan

Why B: In PRINCE2, the Project Board requests a detailed plan for the next stage, which is the Stage Plan. The Stage Plan is produced at the end of the current stage (or during Initiation for the first stage) and provides the detailed management and technical steps for the upcoming stage, aligning with the 'Managing a Stage Boundary' process. This plan is essential for the Project Board to approve the continuation of the project into the next stage.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.