Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which document is the key output of the Initiating a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Initiation Documentation

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, containing the business case, project plan, and other baselines.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Business Case

    Why it's wrong here

    The Business Case is developed in Starting Up a Project and refined here, but the PID is the overall output.

  • Project Initiation Documentation

    Why this is correct

    The PID is the comprehensive set of documents that form the project baseline.

  • Project Plan

    Why it's wrong here

    The Project Plan is part of the PID, not the whole output.

  • Stage Plan

    Why it's wrong here

    Stage Plans are produced during Managing a Stage Boundary.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.