PRINCE2F PRINCE2 Practices Practice Question
In PRINCE2, who is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Project Manager
The Project Manager maintains the Business Case, but the Executive (SRO) owns it and is ultimately responsible for ensuring business justification.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Project Manager
Why this is correct
The Project Manager maintains the Business Case on behalf of the Executive.
- ✗
The Project Support
Why it's wrong here
Project Support provides administrative support, not maintenance of the Business Case.
- ✗
The Executive
Why it's wrong here
The Executive owns the Business Case but does not maintain it day-to-day.
- ✗
The Senior User
Why it's wrong here
The Senior User represents users but does not maintain the Business Case.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.