In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

⚠ Common exam trap

PRINCE2F often tests the accountability-vs-responsibility split, so the trap is picking the Executive (who owns the Business Case) instead of the Project Manager (who maintains it).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Manager

In PRINCE2 the Project Manager is responsible for maintaining the Business Case throughout the project, updating it at each stage boundary and whenever a change or exception affects justification. The Executive owns and is accountable for the Business Case, but the day-to-day maintenance is delegated to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    The Project Manager

    Why this is correct

    PRINCE2 assigns the Project Manager day-to-day responsibility for maintaining and updating the Business Case, including benefits reviews and tolerances. The Executive owns it and the Senior User champions benefits, but upkeep sits with the Project Manager.

  • ✗

    The Project Support

    Why it's wrong here

    Project Support provides administrative assistance such as maintaining logs and configuration records, but the Business Case is owned by the Executive. It is tempting because support staff handle documentation, and Project Support would be correct for maintaining the project's administrative files rather than the Business Case.

  • ✗

    The Executive

    Why it's wrong here

    The Executive owns the Business Case and is accountable for its viability, but day-to-day maintenance and updating falls to the Project Manager. The Executive is tempting because accountability for the Business Case sits there, yet the question asks who maintains it. The Executive would be correct if asked who is accountable.

  • ✗

    The Senior User

    Why it's wrong here

    The Senior User represents user interests and specifies requirements, but accountability for the Business Case rests with the Executive, who owns the justification. It is tempting because the Senior User supplies benefits information, and that role would be correct for defining and verifying the project's expected benefits.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.