PRINCE2F People: organizations, teams, and leadership Practice Question
How often should the Project Board meet during a PRINCE2 project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
At the end of each stage and when exceptions occur
Project Board meetings are held at key decision points (end of stages) and when exceptions occur. They are not scheduled at regular intervals but are exception-driven.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Only at the end of the project
Why it's wrong here
The Board meets at the end of each stage, not just at project closure.
- ✗
Monthly
Why it's wrong here
Monthly meetings are not prescribed; meetings are exception-driven.
- ✗
Weekly
Why it's wrong here
Weekly meetings are not typical; the Project Board meets at key decision points.
- ✓
At the end of each stage and when exceptions occur
Why this is correct
The Project Board meets at stage boundaries and when an exception is raised.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.