Courseiva
Overview of PRINCE2 and PrinciplesmediumDrag & DropObjective-mapped

PRINCE2F Overview of PRINCE2 and Principles Practice Question

Drag and drop the steps of the PRINCE2 Starting up a Project process into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1. Appoint the Executive and the Project Manager, 2. Capture previous lessons, 3. Design and appoint the project management team, 4. Prepare the outline Business Case, 5. Select the project approach and assemble the Project Brief

The Starting up a Project process ensures that the prerequisites for initiating a project are in place, starting with appointing key roles, then learning from past projects, building the team, developing the outline business case, and finally selecting the approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1. Appoint the Executive and the Project Manager, 2. Capture previous lessons, 3. Design and appoint the project management team, 4. Prepare the outline Business Case, 5. Select the project approach and assemble the Project Brief

    Why this is correct

    This is the correct order because the PRINCE2 methodology dictates that leadership roles are established first, then lessons are reviewed, the team is built, the business case is outlined, and finally the approach is selected to define how the project will proceed.

  • 1. Appoint the Executive and the Project Manager, 2. Capture previous lessons, 4. Prepare the outline Business Case, 3. Design and appoint the project management team, 5. Select the project approach and assemble the Project Brief

    Why it's wrong here

    This order is incorrect because the Business Case should be prepared after the project management team is appointed; the team contributes to the business case. Placing it before team appointment can lead to an unrealistic outline.

  • 1. Appoint the Executive and the Project Manager, 3. Design and appoint the project management team, 2. Capture previous lessons, 4. Prepare the outline Business Case, 5. Select the project approach and assemble the Project Brief

    Why it's wrong here

    This order is incorrect because capturing previous lessons should occur before designing the team to ensure lessons are incorporated into team roles and responsibilities. Skipping lessons early may repeat past mistakes.

  • 1. Appoint the Executive and the Project Manager, 2. Capture previous lessons, 3. Design and appoint the project management team, 5. Select the project approach and assemble the Project Brief, 4. Prepare the outline Business Case

    Why it's wrong here

    This order is incorrect because the project approach should be selected based on the outline Business Case, not before it. The business case justifies the project and influences the choice of approach.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.