Why does PRINCE2 recommend separating the role of Project Manager from Project Assurance?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To provide an independent perspective on the project's status
Separating Project Manager from Project Assurance ensures objectivity and independence of assurance activities. The Project Manager is responsible for day-to-day management and cannot objectively assess their own work.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To comply with regulatory requirements
Why it's wrong here
The separation is a recommended practice for objectivity, not necessarily regulatory.
- ✗
To reduce the workload of the Project Manager
Why it's wrong here
While it may reduce workload, the primary reason is independence.
- ✓
To provide an independent perspective on the project's status
Why this is correct
Independence is key to effective assurance.
- ✗
To allow the Project Manager to focus on quality reviews
Why it's wrong here
Quality reviews can involve the Project Manager; separation is not for this reason.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.