Which THREE of the following are roles on the PRINCE2 Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior Responsible Owner (Executive)
The Project Board consists of the Senior Responsible Owner (Executive), Senior User, and Senior Supplier.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The PM is not on the Project Board; they report to it.
- ✓
Senior Responsible Owner (Executive)
Why this is correct
Yes, this is the chair of the Project Board.
- ✓
Senior User
Why this is correct
Represents the users' interests.
- ✓
Senior Supplier
Why this is correct
Represents the suppliers' interests.
- ✗
Team Manager
Why it's wrong here
Team Managers are not on the Project Board.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.