In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?
Crashing saves 3 days for $3,000, giving $1,000 per day. This directly satisfies the stem's request for the crash cost per day, derived by dividing the additional cost by the days compressed on the critical path activity.
Why this answer
The crash cost per day is calculated by dividing the additional cost by the number of days saved. Activity X can be crashed from 10 days to 7 days, saving 3 days, at an additional cost of $3,000. Therefore, $3,000 / 3 days = $1,000 per day.
Exam trap
PK0-005 often tests the calculation of crash cost per day, and candidates may mistakenly divide by the original duration or the crash duration instead of the days saved.
How to eliminate wrong answers
Option B is wrong because $500 per day would result from dividing $3,000 by 6 days, which is not the number of days saved. Option C is wrong because $3,000 per day would be the total additional cost, not per day. Option D is wrong because $300 per day would result from dividing $3,000 by 10 days, which is the original duration, not the days saved.