Courseiva

CCNA Pkp Project Lifecycle Questions

75 of 188 questions · Page 1/3 · Pkp Project Lifecycle topic · Answers revealed

1
MCQhard

In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?

A.$1,000 per day
B.$500 per day
C.$3,000 per day
D.$300 per day
AnswerA

Crashing saves 3 days for $3,000, giving $1,000 per day. This directly satisfies the stem's request for the crash cost per day, derived by dividing the additional cost by the days compressed on the critical path activity.

Why this answer

The crash cost per day is calculated by dividing the additional cost by the number of days saved. Activity X can be crashed from 10 days to 7 days, saving 3 days, at an additional cost of $3,000. Therefore, $3,000 / 3 days = $1,000 per day.

Exam trap

PK0-005 often tests the calculation of crash cost per day, and candidates may mistakenly divide by the original duration or the crash duration instead of the days saved.

How to eliminate wrong answers

Option B is wrong because $500 per day would result from dividing $3,000 by 6 days, which is not the number of days saved. Option C is wrong because $3,000 per day would be the total additional cost, not per day. Option D is wrong because $300 per day would result from dividing $3,000 by 10 days, which is the original duration, not the days saved.

2
Multi-Selecthard

During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).

Select 3 answers
A.Risk register
B.Issue log
C.Work Breakdown Structure
D.Communication management plan
E.Stakeholder register
AnswersB, D, E

The issue log records active problems, their owners and resolution status, so reviewing it exposes communication breakdowns already logged as issues and shows which stakeholder updates have stalled. It directly satisfies the stem's constraint that stakeholders are not receiving timely updates, letting the project manager trace unresolved communication items and assign corrective action.

Why this answer

The Issue log (B) is correct because it records active problems such as the team's communication struggles and stakeholders missing updates, letting the project manager track and resolve these execution-phase issues. The Communication management plan (D) is correct because it defines who receives what information, in what format, and at what frequency, so reviewing it directly reveals and corrects the gaps in timely stakeholder updates. The Stakeholder register (E) is correct because it identifies each stakeholder's communication requirements, expectations, and influence, which is essential for targeting the right updates to the right people.

The Risk register (A) is not selected because it deals with potential future uncertainties rather than the current, realized communication problem. The Work Breakdown Structure (C) is not selected because it only decomposes project scope and deliverables and contains no communication or stakeholder information.

Exam trap

PK0-005 often tests the confusion between documents that are relevant to communication (communication management plan, stakeholder register, issue log) and those that are not (risk register, WBS), and candidates may incorrectly include risk register because risks can affect communication.

3
MCQmedium

A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?

A.Bottom-up estimation
B.Parametric estimation
C.Analogous estimation
D.Three-point estimation
AnswerC

Analogous estimation uses historical data from a comparable past project, adjusted for size and complexity, to derive the current estimate. The reliance on a similar prior project rather than decomposed work packages identifies this technique.

Why this answer

Analogous estimation uses historical data from a similar past project as the basis for estimating the current project, then adjusts for known differences such as size and complexity. This top-down approach is quick and requires less detailed information, making it ideal when limited data is available. The key is that the estimate is derived from analogy to a comparable project, not from a mathematical model or detailed breakdown.

Exam trap

PK0-005 often tests the confusion between analogous estimation and parametric estimation, as both use historical data; the key differentiator is that analogous uses a similar project as a whole, while parametric uses a statistical relationship per unit.

How to eliminate wrong answers

Option A is wrong because bottom-up estimation involves estimating the cost of individual work packages or activities and then aggregating them to get the total project cost, which requires a detailed WBS and is more time-consuming. Option B is wrong because parametric estimation uses a statistical relationship between historical data and other variables (e.g., cost per line of code) to calculate an estimate, often using regression analysis or unit rates, rather than adjusting a similar project's overall cost. Option D is wrong because three-point estimation uses three estimates (optimistic, pessimistic, and most likely) to define an approximate range and calculate a weighted average (e.g., PERT), which is a probabilistic technique, not based on analogy.

4
MCQhard

During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?

A.Risk register
B.Issue log
C.Change request log
D.Lessons learned
AnswerA

Logging the newly identified risk in the risk register satisfies the stem's requirement to record it during execution. The register is the single repository capturing each risk's description, probability, impact, owner, and response, so assessment outputs and tracking updates are appended there as the risk lifecycle progresses.

Why this answer

The risk register is the correct answer because it is the formal document where all identified risks, including newly discovered ones during execution, are recorded, assessed, and tracked. When a team member identifies a potential risk not previously documented, the project manager logs it in the risk register and then performs qualitative and quantitative risk analysis to determine its probability and impact. This ensures the risk is managed alongside all other project risks.

Exam trap

PK0-005 often tests the distinction between risk register (potential future events) and issue log (current problems), so candidates must recognize that a newly identified risk belongs in the risk register even if discovered during execution.

How to eliminate wrong answers

Option B is wrong because the issue log records problems that have already occurred and are impacting the project, not potential future risks. Option C is wrong because the change request log tracks formal requests to modify project scope, schedule, or budget, not risk identification. Option D is wrong because lessons learned is a repository of knowledge gained from past projects or phases, used for continuous improvement, not for tracking active risks.

5
Multi-Selecteasy

Which TWO documents are typically created during the project initiating phase?

Select 2 answers
A.Stakeholder register
B.Status report
C.Project charter
D.Work breakdown structure
E.Risk register
AnswersA, C

The stakeholder register is produced during initiating, alongside the project charter, as the output that identifies everyone with an interest in the project. It satisfies the stem's requirement for an initiating-phase document because stakeholder identification happens before planning begins.

Why this answer

The project initiating phase produces the documents that formally authorize the project and begin identifying the people involved. Option C, the project charter, is correct because it is the document that formally authorizes the existence of the project and gives the project manager authority to apply organizational resources to project activities. Option A, the stakeholder register, is correct because stakeholder identification is performed during initiating, and the stakeholder register is the output that records identified stakeholders and relevant information about them.

Option B, the status report, is not part of initiating; status reports are created during project execution and monitoring/controlling to communicate progress. Option D, the work breakdown structure, is not part of initiating; the WBS is created during project planning as part of scope management. Option E, the risk register, is not part of initiating; it is an output of the risk management processes performed during planning.

Exam trap

The trap is that candidates mix up artifacts from different process groups — status reports, WBS, and risk register sound project-related but belong to Executing/Monitoring or Planning, not Initiating.

6
Multi-Selectmedium

A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)

Select 2 answers
A.The project is on schedule.
B.The project is ahead of schedule.
C.The project is under budget.
D.The project is behind schedule.
E.The project is over budget.
AnswersB, E

SPI > 1 indicates ahead of schedule.

Why this answer

CPI < 1 means over budget; SPI > 1 means ahead of schedule.

7
MCQmedium

Which of the following is the primary purpose of a feasibility study during the initiating phase?

A.To develop a communication plan
B.To identify all project risks
C.To create a detailed project schedule
D.To determine if the project is viable
AnswerD

A feasibility study evaluates technical, economic, legal, and scheduling factors to establish whether a project can realistically deliver its objectives within existing constraints. During the initiating phase, this assessment determines viability before resources are committed, directly satisfying the stem's requirement to identify the primary purpose.

Why this answer

A feasibility study is conducted during the initiating phase to evaluate whether a proposed project is technically, financially, legally, and operationally viable before committing resources. It answers the question 'should we proceed?' by analyzing alternatives and constraints. Communication plans, risk identification, and detailed schedules come later in the planning phase.

Exam trap

The trap is confusing initiating-phase activities with planning-phase deliverables — candidates pick 'identify all project risks' or 'create a detailed schedule' because those sound important, but they belong to planning, not feasibility.

How to eliminate wrong answers

Option A is wrong because the communication plan is developed during the planning phase, not the initiating phase, and is not the purpose of a feasibility study. Option B is wrong because risk identification occurs during planning (and continues throughout), while feasibility focuses on viability, not exhaustive risk enumeration. Option C is wrong because the detailed project schedule is a planning-phase artifact created after the project is approved.

8
MCQmedium

During the Initiating phase of a construction project, the project manager learns that the sponsoring organization will not commit funding until the document that formally authorizes the project and names the project manager exists. Which document should the project manager produce?

A.Work breakdown structure
B.Project charter
C.Business case
D.Project management plan
AnswerB

The project charter formally authorizes the existence of the project and gives the project manager authority to apply organizational resources to project activities. CompTIA Project+ places charter creation in the Initiating phase. Because the sponsor requires a document that both authorizes the project and names the project manager before releasing funding, the charter is exactly the artifact needed to satisfy that condition.

Why this answer

A project charter formally authorizes the project and designates the project manager with the authority to apply resources. The sponsoring organization's condition ties funding to that authorization, so the charter is the required deliverable in Initiating. The project management plan and WBS come later in Planning, while the business case justifies investment but does not authorize the project.

Exam trap

The trap here is confusing the business case, which justifies the investment, with the project charter, which formally authorizes the project and names the project manager.

9
Multi-Selectmedium

A project manager is preparing for the Closing phase of a project that has been completed successfully. Which TWO activities are part of the Close Project or Phase process? (Choose two.)

Select 2 answers
A.Identify stakeholders and analyze their interest and influence on the project.
B.Obtain final acceptance of the project deliverables from the customer or sponsor.
C.Develop the project management plan and gain approval from the sponsor.
D.Archive project documents and capture lessons learned for future projects.
E.Estimate activity durations and develop the project schedule.
AnswersB, D

Obtaining final acceptance of deliverables is a key activity in the Close Project or Phase process. It confirms that the project's products, services, or results meet the agreed requirements and that the customer or sponsor formally accepts them. This acceptance is necessary before the project can be considered complete and before final payments and resource release occur.

Why this answer

The Close Project or Phase process includes obtaining final acceptance of deliverables, archiving project documents, capturing lessons learned, releasing resources, and finalizing financial and procurement closure. Developing the project management plan, identifying stakeholders, and estimating activity durations are all earlier-phase activities that do not belong in Closing. Final acceptance and lessons learned are specifically part of closure.

Exam trap

The trap here is mixing planning and initiating activities, such as developing the project management plan or identifying stakeholders, into the Closing phase, when closure focuses on acceptance, archiving, and lessons learned.

10
Multi-Selectmedium

A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?

Select 2 answers
A.Delaying a critical path activity delays the project.
B.Critical path activities can have negative float.
C.Activities on the critical path have positive float.
D.There can be only one critical path.
E.It has the longest duration in the project.
AnswersA, E

Critical path activities have zero float, so any delay directly extends the project's finish date. This satisfies the stem's requirement for a true statement about critical path behaviour: the path determines the shortest possible duration, and slack-free tasks on it transmit their slippage straight to overall completion.

Why this answer

Option A is correct because the critical path is defined as the sequence of activities with zero total float, so any delay to an activity on it directly pushes out the project finish date. Option E is correct because the critical path is, by definition, the longest-duration path through the network diagram, which determines the shortest possible project completion time. Option B is wrong because negative float indicates a schedule that is already behind its imposed deadline, not a normal property of critical path activities.

Option C is wrong because critical path activities have zero float, not positive float; positive float belongs to non-critical activities. Option D is wrong because a network diagram can contain multiple critical paths when two or more sequences share the same longest duration.

Exam trap

The trap is assuming there is only one critical path or that critical activities have positive float, when in fact they have zero float and multiple critical paths can exist.

11
MCQmedium

A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?

A.Three-point estimation
B.Analogous estimation
C.Bottom-up estimation
D.Parametric estimation
AnswerB

Analogous estimation uses historical cost data from a comparable past project to derive the new estimate, which directly matches the top-down approach described. It satisfies the stem's constraint of relying on a similar project's actuals rather than decomposing deliverables, making it fast and inexpensive, though less precise than bottom-up methods.

Why this answer

Analogous estimation uses historical data from a similar past project to estimate the current project's cost or duration, typically at a high level (top-down). Because the question specifies a top-down approach based on historical data from a similar project, analogous estimation is the exact match. It is fast and useful early when detailed information is scarce, though less precise than bottom-up methods.

Exam trap

PK0-005 often tests the confusion between analogous (historical analogy) and parametric (unit-rate model) estimation, so candidates must identify whether the basis is a similar project or a statistical relationship.

How to eliminate wrong answers

Option A is wrong because three-point estimation uses optimistic, pessimistic, and most-likely values (often with PERT weighting) to compute an expected estimate, not historical comparison to a similar project. Option C is wrong because bottom-up estimation aggregates estimates from individual work packages or tasks, which is the opposite of a top-down approach. Option D is wrong because parametric estimation uses a statistical relationship between historical data and variables (e.g., cost per square foot, cost per line of code), not a direct analogy to one similar project.

12
MCQmedium

A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?

A.Keep satisfied
B.Monitor
C.Manage closely
D.Keep informed
AnswerC

Stakeholders rated high on both power and interest demand the closest engagement, since they can significantly influence the project and care deeply about outcomes. The power/interest grid assigns this quadrant the manage closely strategy, maximising involvement and addressing concerns directly.

Why this answer

In the power/interest grid, stakeholders with both high power and high interest must be managed closely because they can significantly influence the project and care deeply about its outcomes. This quadrant requires proactive engagement, frequent communication, and involvement in key decisions. The other quadrants (keep satisfied, keep informed, monitor) apply to different combinations of power and interest.

Exam trap

The trap is mixing up the four quadrant labels — candidates often confuse 'manage closely' with 'keep satisfied' because both involve high-power stakeholders, but only high interest triggers close management.

How to eliminate wrong answers

Option A is wrong because 'keep satisfied' applies to high-power, low-interest stakeholders who need to be kept content but not over-communicated with. Option B is wrong because 'monitor' applies to low-power, low-interest stakeholders who require minimal effort. Option D is wrong because 'keep informed' applies to low-power, high-interest stakeholders who need updates but have limited influence.

13
Multi-Selectmedium

A project manager is executing a project and a team member reports that a purchased component does not meet the specifications stated in the procurement agreement. The project manager must document and pursue a remedy. Which TWO activities should the project manager perform? (Choose two.)

Select 2 answers
A.Perform a procurement audit and update the lessons learned register with the audit findings.
B.Terminate the contract immediately and re-procure the component from a different seller.
C.Accept the component conditionally and close the procurement, then negotiate a credit later.
D.Use the agreed inspection, quality, and acceptance criteria to verify the deliverable formally.
E.Record the nonconformance and issue a formal claim or dispute notice to the seller.
AnswersD, E

The procurement agreement contains inspection, quality, and acceptance criteria that govern whether deliverables conform. Applying those criteria through formal inspection and acceptance verification produces documented evidence of the nonconformance, which is required before a claim can be substantiated. Without this verification step, the buyer cannot demonstrate that the seller failed to meet the contractually stated specifications.

Why this answer

A defective seller deliverable is handled through contract administration: verify conformance against the agreed inspection and acceptance criteria, document the nonconformance, and pursue a formal claim or dispute notice under the procurement agreement. Audits and closure are separate processes, and unilateral termination is a disproportionate remedy that bypasses contractual dispute procedures.

Exam trap

The trap here is treating a seller nonconformance as a quality-only or closure issue, when it is fundamentally a contract administration and claims matter.

14
MCQmedium

A change request is submitted to add a new feature to a project. What is the first step the project manager should take?

A.Implement the change
B.Perform impact analysis
C.Update the project plan
D.Submit to change control board
AnswerB

Impact analysis must precede any decision on a change request, examining effects on scope, schedule, cost and risk. It satisfies the stem's constraint of identifying the first step, since the change control board cannot approve or reject without that assessment.

Why this answer

When a change request is submitted, the project manager's first step is to perform an impact analysis to assess how the change affects scope, schedule, cost, quality, risk, and resources. Only after this analysis is documented can the request be reviewed by the change control board (CCB) for approval or rejection. Implementing or updating the plan before analysis would bypass the integrated change control process.

Exam trap

PK0-005 often tests the sequence of integrated change control; the trap is selecting 'submit to CCB' as the first step, when impact analysis must precede CCB review so the board has the data needed to decide.

How to eliminate wrong answers

Option A is wrong because implementing a change before analysis and approval violates integrated change control and can introduce unvetted scope, cost, and schedule impacts. Option C is wrong because updating the project plan happens only after the change is approved and the impact is understood; doing it first would document an unapproved change. Option D is wrong because submitting to the CCB is a later step that should occur after the PM has gathered impact analysis data so the board can make an informed decision.

15
MCQeasy

A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?

A.The project is over budget
B.The project is behind schedule
C.The project is on schedule
D.The project is ahead of schedule
AnswerB

SPI is calculated as earned value divided by planned value. A result of 0.9 means only 90 per cent of the work scheduled has been earned, so the project is progressing slower than planned. Any SPI below 1.0 indicates the project is behind schedule.

Why this answer

SPI (Schedule Performance Index) = EV / PV. An SPI less than 1 means the project is behind schedule. 0.9 indicates that for every planned unit of work, only 0.9 units have been completed.

16
MCQmedium

A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?

A.Keep informed
B.Monitor
C.Manage closely
D.Keep satisfied
AnswerC

High power combined with high interest places this executive in the quadrant demanding the closest engagement, so the project manager must manage closely. This satisfies the grid's requirement for regular, detailed communication and active involvement, ensuring their significant authority and stake are addressed throughout the project.

Why this answer

In the power/interest grid, a stakeholder with both high power and high interest falls into the 'Manage Closely' quadrant. These stakeholders have the authority to influence project decisions and are deeply invested in outcomes, so they require active, ongoing engagement and collaboration. The PM should involve them in decision-making and keep a close working relationship.

Exam trap

PK0-005 often tests the power/interest grid by swapping the strategies for the high-power quadrants — candidates confuse 'Manage Closely' (high power + high interest) with 'Keep Satisfied' (high power + low interest).

How to eliminate wrong answers

Option A is wrong because 'Keep Informed' applies to low-power, high-interest stakeholders who need updates but cannot affect the project. Option B is wrong because 'Monitor' applies to low-power, low-interest stakeholders who require minimal effort. Option D is wrong because 'Keep Satisfied' applies to high-power, low-interest stakeholders who must be placated but not over-engaged.

17
MCQmedium

During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?

A.7 days
B.8 days
C.9 days
D.12 days
AnswerC

Two paths exist: A then C totals 5+4=9 days, while B alone totals 3 days. The critical path is the longest, so 9 days governs the project duration. This satisfies the stem's requirement to identify the critical path duration from the given dependencies.

Why this answer

The critical path is the longest sequence of dependent activities. Path A→C takes 5 + 4 = 9 days, while path B takes 3 days. Since A and B run in parallel and C depends on A, the project duration is determined by the longer path, A→C, which equals 9 days.

Exam trap

PK0-005 often tests critical path by including a shorter parallel branch — candidates mistakenly add all activity durations or pick the sum of the two starting activities instead of tracing the longest dependent path.

How to eliminate wrong answers

Option A (7 days) is wrong because it incorrectly adds B's duration to C or misapplies dependencies. Option B (8 days) is wrong because it likely adds A and B (5+3) without accounting for C's dependency on A. Option D (12 days) is wrong because it sums all three durations (5+3+4) as if they were sequential, ignoring the parallel structure.

18
MCQeasy

A project manager identifies a key stakeholder who has high interest in the project but low power to influence decisions. In the power/interest grid, where should this stakeholder be placed?

A.Manage closely
B.Keep satisfied
C.Monitor
D.Keep informed
AnswerD

High interest with low power maps to the "keep informed" quadrant of the power/interest grid, satisfying the stakeholder's need for regular project updates without granting decision-making influence. Engagement focuses on communication rather than consultation, ensuring the stakeholder stays aware while the project manager avoids unnecessary approval cycles with someone who cannot affect outcomes.

Why this answer

In the power/interest grid, stakeholders with high interest but low power should be kept informed. They care about the project and want updates, but they cannot significantly influence decisions, so the appropriate strategy is regular communication to maintain their engagement without over-investing management effort. 'Keep satisfied' is reserved for high-power, low-interest stakeholders.

Exam trap

PK0-005 often tests the power/interest grid by swapping the strategies for the high-interest/low-power and high-power/low-interest quadrants; the trap is confusing 'keep informed' with 'keep satisfied' when the stakeholder's power level is low.

How to eliminate wrong answers

Option A (Manage closely) is wrong because that quadrant is for stakeholders with both high power and high interest, who require close, ongoing engagement. Option B (Keep satisfied) is wrong because that quadrant applies to high-power, low-interest stakeholders whose needs must be met to avoid obstruction, but who do not need frequent detailed updates. Option C (Monitor) is wrong because that quadrant is for low-power, low-interest stakeholders who require minimal effort and periodic monitoring only.

19
MCQmedium

Which contract type places the most cost risk on the seller?

A.Fixed-price
B.Cost-reimbursable
C.Time and materials
D.Cost plus incentive fee
AnswerA

A fixed-price contract locks the seller into an agreed sum regardless of actual costs, so any overrun is absorbed by the seller. This places maximum cost risk on the seller, unlike cost-reimbursable or time-and-materials arrangements.

Why this answer

A fixed-price contract puts cost risk on the seller because the price is fixed regardless of actual costs.

20
MCQmedium

A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?

A.Decomposition
B.Bottom-up estimating
C.Precedence diagramming
D.Rolling wave planning
AnswerA

Decomposition subdivides project deliverables into progressively smaller, manageable work packages, satisfying the WBS constraint of hierarchical breakdown. It is the specific technique that transforms top-level deliverables into assignable, estimable components at the lowest WBS level.

Why this answer

Decomposition is the technique used to break down project deliverables into smaller, more manageable components, ultimately producing work packages at the lowest level of the WBS. It involves subdividing scope and deliverables into progressively finer levels until the work can be estimated, scheduled, and assigned. This is the core technique of the Create WBS process.

Exam trap

PK0-005 often tests the distinction between WBS creation techniques and estimation/scheduling techniques; the trap is selecting 'bottom-up estimating' or 'rolling wave planning' because they sound like breakdown methods, when only decomposition produces the WBS hierarchy.

How to eliminate wrong answers

Option B (Bottom-up estimating) is wrong because it is a cost estimation technique that aggregates estimates from the lowest level of the WBS upward, not a decomposition technique for building the WBS itself. Option C (Precedence diagramming) is wrong because it is a schedule network diagramming method (PDM) used to sequence activities, not to break down deliverables. Option D (Rolling wave planning) is wrong because it is an iterative planning technique where work near-term is detailed while future work is planned at a higher level; it complements but does not define the decomposition of deliverables.

21
MCQmedium

A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?

A.Parametric estimation
B.Three-point estimation
C.Bottom-up estimation
D.Analogous estimation
AnswerD

Analogous estimation derives cost from the actual cost of a comparable historical project, then scales it for differences in size and complexity. This top-down, experience-based approach matches the scenario, unlike parametric or bottom-up methods that build estimates from component detail.

Why this answer

Analogous estimation uses historical data from a similar past project as the basis for estimating the current project's cost, then adjusts for known differences in size, complexity, or scope. This is exactly what the project manager is doing — referencing actual costs of a comparable project and scaling them. It is a top-down, expert-judgment-driven technique that is fast but less accurate than detailed methods.

Exam trap

PK0-005 often tests the confusion between analogous (single comparable project, top-down) and parametric (statistical formula with unit rates) estimation, since both rely on historical data — candidates must identify whether a formula or a single reference project is being used.

How to eliminate wrong answers

Option A is wrong because parametric estimation uses a statistical relationship between historical data and other variables (e.g., cost per line of code, cost per square foot) applied via a formula, not a single analogous project's actual cost. Option B is wrong because three-point estimation uses optimistic, pessimistic, and most likely estimates (PERT/beta distribution) to compute an expected value, which is unrelated to adjusting a past project's cost. Option C is wrong because bottom-up estimation aggregates estimates from individual work packages or tasks, which is the opposite of the top-down analogous approach described.

22
MCQmedium

A project manager uses a power/interest grid to categorize stakeholders. Stakeholders with high power and low interest should be managed using which approach?

A.Manage closely
B.Keep informed
C.Keep satisfied
D.Monitor
AnswerC

High-power, low-interest stakeholders can block or derail the project, so they must be kept satisfied through regular, concise updates that address their concerns without overloading them. This prevents disengagement from turning into active opposition when decisions require their approval.

Why this answer

High power, low interest stakeholders need to be kept satisfied to prevent them from using their power against the project.

23
Multi-Selectmedium

A project manager is conducting a lessons learned session at the end of a project. Which TWO activities are typically performed during project closure? (Select two.)

Select 2 answers
A.Archiving project documents
B.Developing the project charter
C.Creating the work breakdown structure
D.Performing risk identification
E.Obtaining formal acceptance from the sponsor
AnswersA, E

Project closure requires consolidating and storing all artefacts — plans, contracts, reports and lessons learned — so they remain available for audit and future projects. Archiving project documents preserves this organisational knowledge and formally releases the records once the deliverable has been accepted.

Why this answer

Option A (Archiving project documents) is correct because project closure includes collecting, indexing, and storing all project records, deliverables, and lessons learned in the organizational knowledge base for future reference and audit purposes. Option E (Obtaining formal acceptance from the sponsor) is correct because closure requires verifying that deliverables meet requirements and securing the sponsor's sign-off, which formally confirms the project's completion. Option B (Developing the project charter) is incorrect because the charter is created during project initiation to authorize the project, not at closure.

Option C (Creating the work breakdown structure) is incorrect because the WBS is developed during project planning to decompose scope into manageable work packages. Option D (Performing risk identification) is incorrect because risk identification is an ongoing activity primarily performed during planning and monitoring, not a typical closure activity.

Exam trap

The trap is that 'lessons learned' appears in the question stem, tempting candidates to pick a distractor tied to it, but the question asks which activities are performed during closure — the exam tests whether you can map activities to the correct Process Group (Initiating, Planning, Executing, Monitoring/Controlling, Closing).

24
MCQhard

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. Which TWO statements are true regarding the project's performance? (Choose two.)

A.The project is ahead of schedule.
B.The project is over budget.
C.The project is behind schedule.
D.The project is under budget.
AnswerB, C

Cost Performance Index equals EV divided by AC, giving 50,000/55,000, which is below 1.0. A CPI under 1.0 means each unit of work costs more than planned, so the project is over budget, satisfying the over-budget condition in the stem.

Why this answer

SPI = EV/PV = 50/60 = 0.83 (<1, behind schedule). CPI = EV/AC = 50/55 = 0.91 (<1, over budget).

25
Multi-Selecthard

During the Planning phase, a project manager is building the work breakdown structure (WBS) for a construction project. Which TWO characteristics must the WBS satisfy? (Choose two.)

Select 2 answers
A.Work packages are decomposed to a level where cost and duration can be reliably estimated.
B.Every element is organized by the organizational reporting structure rather than by deliverable.
C.The 100 percent rule is applied so all project work is captured and nothing extraneous is included.
D.The WBS is decomposed until every activity has a duration of exactly one day.
E.Each work package is assigned to at least one external vendor for execution.
AnswersA, C

A valid WBS decomposes deliverables into work packages that are small enough for accurate estimating, scheduling, and control. If a work package is too broad, estimates become unreliable and tracking progress is difficult. This characteristic supports the planning goal of creating a manageable, measurable scope baseline that the team can execute and monitor effectively.

Why this answer

A sound WBS follows the 100 percent rule and decomposes deliverables into work packages detailed enough for reliable estimating and control. Organizing by reporting structure, mandating vendor execution, or forcing one-day durations are not WBS requirements and would undermine the deliverable-oriented structure needed for scope management.

Exam trap

The trap here is treating the WBS as a task list or org chart, when it is a deliverable-oriented hierarchy governed by the 100 percent rule.

26
Multi-Selectmedium

A project manager is preparing for the Closing phase of a project that involved an external vendor. Which TWO activities are essential to formally close the project? (Choose two.)

Select 2 answers
A.Conduct a procurement audit and close the contract with the vendor.
B.Develop the project management plan and gain sponsor approval.
C.Obtain final acceptance of the product from the customer.
D.Update the stakeholder engagement plan with new communication preferences.
E.Perform a Monte Carlo simulation to reassess schedule risk.
AnswersA, C

A procurement audit reviews the procurement process to identify successes and failures, and closing the contract ensures all terms are met and no further obligations exist. This is essential when an external vendor is involved. It protects the organization legally and financially, and it captures lessons learned for future procurements. It is a key activity in the Closing phase.

Why this answer

Formal project closure requires obtaining final acceptance of the product and closing any procurement contracts, including conducting a procurement audit. These activities ensure the project is legally and administratively complete. Risk simulations, plan development, and stakeholder engagement updates belong to earlier phases and do not finalize the project.

Exam trap

The trap here is selecting ongoing monitoring activities like updating stakeholder plans or performing risk analysis, which are not part of formal closure.

27
MCQhard

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?

A.$200,000
B.$220,000
C.$260,000
D.$240,000
AnswerD

Using EAC = BAC ÷ CPI, with CPI = EV ÷ AC = 100,000 ÷ 120,000 ≈ 0.833, gives 200,000 ÷ 0.833 ≈ $240,000. This satisfies the stem's constraint that remaining work continues at the current cost efficiency, rather than assuming the original budget or schedule-based performance.

Why this answer

CPI = EV/AC = 100,000/120,000 = 0.833. EAC = BAC/CPI = 200,000/0.833 = 240,000.

28
MCQeasy

In which Tuckman stage do team members begin to resolve their differences, establish norms, and develop closer relationships?

A.Storming
B.Norming
C.Performing
D.Forming
AnswerB

Norming is the Tuckman stage where interpersonal conflict subsides and the team coalesces around shared norms and working relationships. Members resolve earlier disagreements and build cohesion here, matching the stem's description of resolving differences and developing closer relationships.

Why this answer

In the Norming stage, team members resolve the conflicts that characterized Storming, agree on working norms, and begin to develop cohesion and trust. This is the stage where ground rules solidify and the team starts functioning as a cooperative unit rather than a collection of individuals.

Exam trap

PK0-005 often tests the boundary between Storming and Norming — candidates pick Storming because they see 'differences' in the question and miss the word 'resolve'.

How to eliminate wrong answers

Option A is wrong because Storming is where conflict and disagreement peak — differences are surfacing, not being resolved. Option C is wrong because Performing is when the team operates at high productivity with interdependence already established; norms are already in place. Option D is wrong because Forming is the orientation stage where members are polite, uncertain, and dependent on the leader — relationships have not yet developed.

29
MCQeasy

During which phase of the project life cycle is the project charter created and stakeholders initially identified?

A.Initiating
B.Closing
C.Executing
D.Planning
AnswerA

The Initiating phase produces the project charter, formally authorising the project and the project manager, and it is where stakeholders are first identified and recorded in the stakeholder register. Both deliverables named in the stem belong to this phase, preceding planning, executing, monitoring and controlling, and closing.

Why this answer

The Initiating phase is where the project charter is authored and approved, and where stakeholders are first identified at a high level. The charter formally authorizes the project, names the project manager, and links the project to organizational strategy — all of which happen before detailed planning begins.

Exam trap

PK0-005 often tests the sequencing of charter vs. stakeholder register — candidates pick Planning because they associate stakeholder analysis with detailed planning work.

How to eliminate wrong answers

Option B is wrong because Closing is where deliverables are handed over, contracts are closed, and lessons learned are captured — no charter work occurs there. Option C is wrong because Executing is where the work defined in the plan is performed; the charter already exists by then. Option D is wrong because Planning follows Initiating and produces subsidiary documents like the project management plan, WBS, and schedule — the charter is an input to planning, not an output.

30
MCQhard

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?

A.Over budget and behind schedule
B.Over budget and ahead of schedule
C.Under budget and behind schedule
D.Under budget and ahead of schedule
AnswerC

CPI above 1.0 means earned value exceeds actual cost, so the project is under budget. SPI below 1.0 means earned value lags planned value, so it is behind schedule. Both indices together confirm cost efficiency with schedule slippage.

Why this answer

CPI is calculated as Earned Value (EV) divided by Actual Cost (AC). A CPI of 1.2 means EV > AC, so the project is under budget (getting more value per dollar spent). SPI is EV divided by Planned Value (PV).

An SPI of 0.8 means EV < PV, so the project is behind schedule. Therefore, the project is under budget and behind schedule.

Exam trap

PK0-005 often tests the direction of EVM indices — candidates confuse which index maps to cost vs. schedule, or invert the >1.0/<1.0 interpretation, leading them to pick the opposite quadrant.

How to eliminate wrong answers

Option A is wrong because a CPI greater than 1.0 indicates under budget, not over budget. Option B is wrong because an SPI less than 1.0 indicates behind schedule, not ahead of schedule. Option D is wrong because an SPI of 0.8 means behind schedule, not ahead — only a value greater than 1.0 would indicate being ahead of schedule.

31
MCQeasy

A project manager is leading a project to develop a new mobile application. The project is in the Executing phase. A team member reports that a key feature cannot be completed as specified due to a technical limitation. The project manager needs to evaluate the impact of this issue on the project constraints. Which document should the project manager review first?

A.Risk register
B.Change log
C.Issue log
D.Project management plan
AnswerC

The issue log is used to document and track issues that arise during the project. It includes details such as the issue description, impact, and assigned owner. In this scenario, the technical limitation is an issue that needs to be evaluated. The project manager should review the issue log to see if this issue has been logged, assess its impact, and determine next steps. It is the primary document for managing issues during execution.

Why this answer

The issue log is the document used to record and manage issues that arise during project execution. When a technical limitation prevents completion of a feature, it is an issue that needs to be documented and assessed. The project manager should review the issue log first to evaluate impact and determine corrective actions.

Exam trap

The trap here is confusing the risk register, which is for potential future events, with the issue log, which is for current problems.

32
MCQhard

A project manager is preparing for the first phase gate review of a new product development effort. The gate requires that predetermined exit criteria be met before the next phase can begin. Which action best demonstrates that the project manager understands the purpose of a phase gate?

A.Initiate the next phase's procurement activities so long-lead items are ordered before the gate decision.
B.Re-baseline the schedule and cost baselines so the next phase starts with accurate targets.
C.Present the completed phase deliverables and obtain a go, no-go, or redirect decision from the governance body.
D.Update the risk register and issue a status report to stakeholders summarizing progress against the baseline.
AnswerC

A phase gate is a decision point where governance reviews deliverables against exit criteria and issues a go, no-go, or redirect decision. Presenting evidence and obtaining that decision is the defining purpose of the gate and controls whether the project proceeds, changes direction, or stops.

Why this answer

A phase gate is a governance decision point where exit criteria are evaluated and the project receives a go, no-go, or redirect decision. Routine reporting, re-baselining, and early procurement are not the gate's purpose and can even undermine it. The correct action is to present deliverables and secure the formal decision.

Exam trap

The trap here is equating a phase gate with ordinary progress reporting or with pre-approving the next phase, when it is actually a formal go or no-go decision point.

33
MCQmedium

A project manager is executing a project when a team member reports that a critical vendor has missed a delivery deadline, threatening the project schedule. Which action should the project manager take FIRST?

A.Assess the impact on the project schedule and evaluate possible corrective actions.
B.Meet with the vendor to negotiate a new delivery date and revise the contract.
C.Update the risk register with the vendor delay and document the impact.
D.Escalate the issue to the sponsor and request additional budget to hire a new vendor.
AnswerA

The project manager's first step is to assess the impact of the vendor delay on the project schedule and then evaluate possible corrective actions. This analysis determines whether the delay can be absorbed, whether fast tracking or crashing is possible, or whether escalation is needed. Taking action without understanding the impact could lead to unnecessary changes or costs.

Why this answer

When a vendor misses a delivery deadline, the project manager should first assess the impact on the project schedule and then evaluate possible corrective actions. This analysis informs whether the issue can be resolved internally or requires escalation. Documenting the issue, negotiating with the vendor, or escalating to the sponsor are subsequent steps that depend on the assessed impact and available options.

Exam trap

The trap here is jumping straight to escalation or vendor negotiation before assessing the actual impact, which can lead to unnecessary changes, costs, or damaged relationships.

34
MCQeasy

A project manager is leading a cross-functional team that is working together for the first time. The team members are polite but hesitant to share ideas. According to Tuckman's stages of group development, which stage is the team currently in?

A.Norming
B.Storming
C.Performing
D.Forming
AnswerD

Forming is marked by politeness and dependence, as members orient themselves to the task and each other without yet challenging ideas. The stem's hesitation to share ideas and superficial courtesy match this initial stage, before storming's conflict or norming's cohesion emerges.

Why this answer

In Tuckman's model, the Forming stage is characterized by politeness, uncertainty, and hesitation as members get to know each other and clarify roles. The team described is polite but reluctant to share ideas, which is the hallmark of Forming, before conflict (Storming) or cohesion (Norming) develops.

Exam trap

The trap is that 'polite but hesitant' sounds positive, so candidates may jump to Norming or Performing; the exam tests whether you recognize that politeness and hesitation are Forming behaviors, not signs of a mature team.

How to eliminate wrong answers

Option A (Norming) is wrong because in Norming the team has resolved conflicts, established norms, and members are comfortable collaborating and sharing — the opposite of hesitant politeness. Option B (Storming) is wrong because Storming involves overt conflict, disagreement over roles and approaches, and resistance — the scenario shows no conflict, only hesitation. Option C (Performing) is wrong because Performing is a high-functioning state where the team works interdependently toward goals with minimal friction, which the hesitant team has not reached.

35
MCQhard

A project manager identifies a risk that could cause a $50,000 loss with a 20% probability. What is the expected monetary value (EMV) of this risk?

A.$10,000
B.$100,000
C.$50,000
D.$25,000
AnswerA

Multiplying the $50,000 loss by the 20% probability yields an EMV of $10,000, which quantifies the risk's average financial exposure for the project budget. This satisfies the stem's requirement to calculate expected monetary value, giving the project manager a defensible figure for contingency reserves and risk prioritisation.

Why this answer

Expected Monetary Value (EMV) for a risk is calculated as probability × impact. Here, EMV = 0.20 × $50,000 = $10,000. This represents the average expected loss from the risk and is used to prioritize risks and build contingency reserves.

Exam trap

The trap is misreading the probability or impact — candidates who use 50% instead of 20%, or who forget to multiply and just pick the impact ($50,000), land on the wrong answer; the exam tests disciplined application of EMV = probability × impact.

How to eliminate wrong answers

Option B ($100,000) is wrong because it appears to multiply impact by 2 or otherwise misapply the formula — it does not correspond to 20% × $50,000. Option C ($50,000) is wrong because it uses the impact alone and ignores the probability, which overstates the expected value. Option D ($25,000) is wrong because it results from using 50% probability instead of 20%, a misreading of the given probability.

36
MCQmedium

In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?

A.Finish-to-Finish (FF)
B.Start-to-Finish (SF)
C.Finish-to-Start (FS)
D.Start-to-Start (SS)
AnswerC

Finish-to-Start defines the successor's start as gated by the predecessor's completion, exactly matching the stem's condition that B begins only after A finishes. The other dependency types (SS, FF, SF) permit overlap or reversed sequencing.

Why this answer

Finish-to-Start (FS) is the most common dependency, where the successor activity cannot start until the predecessor activity has finished.

37
MCQmedium

A project manager is assigning stakeholders to quadrants on a power/interest grid. Which stakeholders require the most active management?

A.Low power, low interest
B.High power, low interest
C.Low power, high interest
D.High power, high interest
AnswerD

High power combined with high interest identifies stakeholders who can both influence project outcomes and care deeply about results, so they demand the most active engagement. Low-power or low-interest quadrants need only periodic monitoring or minimal communication.

Why this answer

In the power/interest grid, stakeholders with both high power (authority to influence decisions) and high interest (stake in the outcome) must be managed closely because they can both affect and are affected by the project. These are typically 'key players' who require active engagement, regular communication, and involvement in decision-making. The PMBOK-aligned strategy for this quadrant is 'Manage Closely.'

Exam trap

PK0-005 often tests whether candidates confuse 'high interest' with 'needs active management' — interest alone doesn't drive active management; power combined with interest does.

How to eliminate wrong answers

Option A is wrong because low power/low interest stakeholders require only minimal monitoring, not active management. Option B is wrong because high power/low interest stakeholders should be 'kept satisfied' with adequate but not intensive communication — they can block the project but don't care about details. Option C is wrong because low power/high interest stakeholders should be 'kept informed' since they care but lack authority to influence outcomes.

38
Multi-Selecthard

During project closure, which three activities should be performed? (Select THREE)

Select 3 answers
A.Obtain formal acceptance
B.Conduct lessons learned
C.Develop project charter
D.Archive project documents
E.Create risk register
AnswersA, B, D

Formal acceptance confirms the customer or sponsor agrees the deliverables meet requirements, authorising closure. Without it the project cannot be signed off or the product transitioned, so obtaining it is a mandatory closure activity alongside handover and lessons learned.

Why this answer

Option A (Obtain formal acceptance) is correct because project closure requires the customer or sponsor to formally sign off on the deliverables, confirming they meet requirements before the project can be officially closed. Option B (Conduct lessons learned) is correct because closure includes capturing what went well, what did not, and recommendations so future projects benefit from the experience. Option D (Archive project documents) is correct because closure involves storing final artifacts, contracts, and records in the organizational knowledge base for audit, compliance, and historical reference.

Option C (Develop project charter) is incorrect because the charter is created during initiation to authorize the project, not at closure. Option E (Create risk register) is incorrect because the risk register is built and maintained during planning and execution, and closure instead focuses on closing out remaining risks.

Exam trap

PK0-005 often tests the confusion between process group activities, tricking candidates into selecting planning or initiating tasks (like charter or risk register) as closure activities.

39
MCQeasy

In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?

A.Keep informed
B.Manage closely
C.Monitor
D.Keep satisfied
AnswerD

High-power, low-interest stakeholders can influence outcomes but do not engage actively, so the keep-satisfied strategy delivers concise, positive updates that prevent surprises without overloading them. Monitor is for low power, manage closely for high interest, keep informed for low power and interest.

Why this answer

In the power/interest grid, stakeholders with high power but low interest must be kept satisfied because they can exert significant influence over the project (e.g., block approvals or funding) yet they don't want to be burdened with day-to-day details. The 'Keep Satisfied' strategy delivers enough high-level information to prevent them from becoming disengaged or obstructive without overwhelming them. This matches the classic Mendelow matrix quadrant mapping: high power/low interest = keep satisfied.

Exam trap

PK0-005 often tests the tendency to confuse 'keep satisfied' with 'keep informed' — candidates assume high-power stakeholders always need frequent communication, but the grid explicitly pairs high power with LOW interest to yield 'keep satisfied,' not 'manage closely.'

How to eliminate wrong answers

Option A (Keep informed) is wrong because 'keep informed' applies to low power/high interest stakeholders who need regular detail but lack authority to derail the project. Option B (Manage closely) is wrong because 'manage closely' is reserved for high power/high interest stakeholders who both care and can influence outcomes. Option C (Monitor) is wrong because 'monitor' is the minimal-effort strategy for low power/low interest stakeholders who require only periodic oversight.

40
Multi-Selectmedium

During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)

Select 3 answers
A.Risk description
B.Probability and impact assessment
C.Actual cost of the project
D.Risk response plan
E.Team member assignments
AnswersA, B, D

A clear risk description states the uncertain event, its cause and potential effect, so the risk can be understood and assessed. It is fundamental register content, providing the basis for subsequent probability, impact and response planning entries.

Why this answer

A risk register typically documents each identified risk with a clear risk description (Option A), so the team understands the nature and cause of the potential problem. It also records the probability and impact assessment (Option B), which quantifies or rates how likely the risk is and how severely it could affect project objectives, enabling prioritization. Additionally, the register includes the risk response plan (Option D), specifying the agreed mitigation, avoidance, transfer, or acceptance strategy along with any contingency actions.

The actual cost of the project (Option C) is tracked in the project budget or cost baseline, not as a core risk register field, and team member assignments (Option E) belong in a responsibility assignment matrix or staffing plan rather than the risk register.

Exam trap

PK0-005 often tests the risk register by including distractors from other project documents (cost, staffing) — candidates must recognize that only risk-specific elements belong in the register.

41
MCQmedium

A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?

A.Three-point estimation
B.Parametric estimation
C.Bottom-up estimation
D.Analogous estimation
AnswerD

Analogous estimation derives duration or cost from the actual figures of a comparable historical project, then scales them for size and complexity differences. Here the manager uses a similar past project's real cost, adjusted for scope variance, satisfying the stem's requirement for a top-down, experience-based estimate rather than bottom-up or parametric calculation.

Why this answer

Analogous estimation uses historical data from a similar past project as the basis for estimating the current project, adjusting for known differences in size, complexity, or scope. The scenario explicitly describes using actual cost of a similar past project with adjustments, which is the textbook definition of analogous (top-down) estimating. It is fast and inexpensive but less accurate than bottom-up or parametric methods.

Exam trap

PK0-005 often tests the confusion between analogous and parametric estimation — candidates see 'historical data' and jump to parametric, but parametric requires a measurable unit rate applied to a variable, whereas analogous uses whole-project comparison.

How to eliminate wrong answers

Option A (Three-point estimation) is wrong because it uses optimistic, pessimistic, and most-likely estimates (often with PERT weighting) to compute an expected value — no historical project cost is referenced. Option B (Parametric estimation) is wrong because it applies a statistical relationship between historical data and other variables (e.g., cost per square foot, cost per line of code) via a unit rate multiplied by quantity, not a whole-project analogy. Option C (Bottom-up estimation) is wrong because it aggregates estimates from the lowest-level WBS work packages upward, which is the most detailed and time-consuming approach — the opposite of the top-down analogy described.

42
MCQmedium

A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?

A.Start-to-Start (SS)
B.Start-to-Finish (SF)
C.Finish-to-Start (FS)
D.Finish-to-Finish (FF)
AnswerA

Activity E can begin as soon as Activity C starts, not after it finishes. That relationship, where the successor's start depends on the predecessor's start, is a Start-to-Start dependency, so SS correctly describes the C-to-E link.

Why this answer

The dependency between Activity C and Activity E is Start-to-Start (SS) because Activity E can start when Activity C starts. In project management, a Start-to-Start relationship means the successor activity cannot begin until the predecessor activity begins. Here, E's start is tied to C's start, not C's finish, so SS is correct.

Exam trap

PK0-005 often tests the distinction between dependency types by describing scenarios where activities overlap or are conditionally linked. Candidates frequently confuse Start-to-Start with Finish-to-Start, especially when the wording implies a sequential relationship. The trap is to assume that because D follows C, E also follows C's finish, but the question explicitly states E starts when C starts.

How to eliminate wrong answers

Option B is wrong because Start-to-Finish (SF) means the successor activity must finish before the predecessor can start, which is not the case here. Option C is wrong because Finish-to-Start (FS) means the successor can start only after the predecessor finishes, but E can start as soon as C starts, not after C finishes. Option D is wrong because Finish-to-Finish (FF) means the successor cannot finish until the predecessor finishes, which is not described.

43
MCQhard

A project manager is analyzing project performance and calculates a cost performance index (CPI) of 0.85 and a schedule performance index (SPI) of 1.10. Which conclusion should the project manager draw from these metrics?

A.The project is under budget and behind schedule.
B.The project is over budget and behind schedule.
C.The project is under budget and ahead of schedule.
D.The project is over budget and ahead of schedule.
AnswerD

A CPI of 0.85 indicates that for every dollar spent, only 85 cents of value is earned, meaning the project is over budget. An SPI of 1.10 means the project is ahead of schedule, as more work is being accomplished than planned. Together, these metrics show cost inefficiency but schedule efficiency.

Why this answer

A CPI below 1.0 means the project is over budget, and an SPI above 1.0 means it is ahead of schedule. Therefore, the project is over budget and ahead of schedule. These indices help the project manager understand cost and schedule efficiency and take appropriate corrective actions.

Exam trap

The trap here is misinterpreting the indices, such as thinking a low CPI means under budget or a high SPI means behind schedule.

44
MCQmedium

In which project management process group is the project charter formally approved, giving the project manager authority to allocate resources?

A.Planning
B.Executing
C.Monitoring and Controlling
D.Initiating
AnswerD

Charter approval occurs during Initiating, where the sponsor formally authorises the project and grants the project manager resource allocation authority. This satisfies the stem's requirement for the process group in which the charter gains approval, distinguishing it from Planning, where the project management plan and subsidiary baselines are developed instead.

Why this answer

The project charter is formally approved during the Initiating process group. This approval authorizes the project and gives the project manager the authority to apply organizational resources to project activities. It is the first formal document that officially starts the project.

Exam trap

PK0-005 often tests process groups by placing charter approval in Planning — candidates must remember that the charter is created and approved in Initiating, before any planning begins.

How to eliminate wrong answers

Option A is wrong because Planning involves developing the project management plan and subsidiary plans, not charter approval. Option B is wrong because Executing involves carrying out the work defined in the plan, which occurs after the charter is approved. Option C is wrong because Monitoring and Controlling tracks performance and manages changes, not project initiation.

45
MCQeasy

During which project phase is the project charter created?

A.Executing
B.Initiating
C.Planning
D.Closing
AnswerB

The project charter is produced during Initiating, where the project is formally authorised and the project manager is assigned. It precedes planning, so it cannot belong to later phases such as Executing, Monitoring and Controlling, or Closing.

Why this answer

The project charter is created during the Initiating phase. This document formally authorizes the project and gives the project manager authority to apply resources. It is a key output of the Initiating process group, specifically the Develop Project Charter process.

Exam trap

PK0-005 often tests the distinction between the Initiating and Planning phases, and candidates may confuse the charter with the project management plan, leading them to select Planning.

How to eliminate wrong answers

Option A is wrong because Executing is where the work is performed according to the project management plan, not where the charter is created. Option C is wrong because Planning involves developing the project management plan and subsidiary plans, not the charter. Option D is wrong because Closing involves finalizing all activities and archiving, not creating the charter.

46
MCQmedium

In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?

A.Start-to-finish (SF)
B.Finish-to-finish (FF)
C.Finish-to-start (FS)
D.Start-to-start (SS)
AnswerD

Start-to-start (SS) dependency defines exactly this relationship: the successor's start is gated by the predecessor's start, not its completion. It satisfies the stem's constraint that the successor cannot begin until the predecessor has begun, distinguishing it from finish-to-start, where the predecessor must finish first.

Why this answer

A Start-to-Start (SS) dependency means the successor activity cannot begin until the predecessor has started. This is the definition given in the question — the successor's start is gated by the predecessor's start, not its finish. SS is commonly used when two activities must run in parallel with a lead/lag relationship.

Exam trap

PK0-005 often tests the four PDM dependency types by swapping the start/finish words; candidates who memorize only FS (the default) misread SS as 'successor finishes when predecessor starts' and pick SF.

How to eliminate wrong answers

Option A is wrong because Start-to-Finish (SF) means the successor cannot finish until the predecessor starts — a rarely used dependency, typically for just-in-time delivery. Option B is wrong because Finish-to-Finish (FF) means the successor cannot finish until the predecessor finishes, governing completion, not start. Option C is wrong because Finish-to-Start (FS) means the successor cannot start until the predecessor finishes — the most common dependency, but it gates on finish, not start.

47
MCQhard

A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?

A.The project is over budget and behind schedule.
B.The project is over budget and ahead of schedule.
C.The project is under budget and ahead of schedule.
D.The project is under budget and behind schedule.
AnswerA

With EV ($50,000) below PV ($60,000), the project is behind schedule, and AC ($55,000) exceeding EV means it is over budget. Both variances are negative, so this statement correctly reflects the earned value metrics given.

Why this answer

The project is over budget and behind schedule because the Cost Performance Index (CPI = EV/AC = $50,000/$55,000 ≈ 0.91) is less than 1, indicating cost overrun, and the Schedule Performance Index (SPI = EV/PV = $50,000/$60,000 ≈ 0.83) is less than 1, indicating schedule slippage. Since EV is lower than both AC and PV, the project has earned less value than planned and spent more than earned.

Exam trap

PK0-005 often tests the confusion between cost and schedule performance indicators, where candidates mistakenly associate EV vs. AC with schedule and EV vs. PV with cost, leading to incorrect conclusions about budget and schedule status.

How to eliminate wrong answers

Option B is wrong because it incorrectly claims the project is ahead of schedule; SPI < 1 means behind schedule, not ahead. Option C is wrong because it incorrectly claims the project is under budget and ahead of schedule; CPI < 1 means over budget, and SPI < 1 means behind schedule. Option D is wrong because it incorrectly claims the project is under budget; CPI < 1 indicates over budget, not under budget.

48
MCQhard

A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?

A.0.83
B.1.10
C.0.91
D.1.20
AnswerC

CPI is earned value divided by actual cost: 50,000 divided by 55,000 equals approximately 0.91. A value below 1.0 indicates the project is over budget for the work completed, since each dollar spent delivered only about 91 cents of earned value.

Why this answer

CPI is calculated as EV divided by AC. With EV = $50,000 and AC = $55,000, CPI = 50,000 / 55,000 = 0.909, which rounds to 0.91. A CPI below 1.0 indicates the project is over budget for the work performed.

Exam trap

The trap here is confusing CPI with SPI or inverting the numerator and denominator — candidates who memorize 'EV over something' without anchoring which denominator belongs to which index will pick 0.83 (SPI) or 1.10 (AC/EV) instead of 0.91.

How to eliminate wrong answers

Option A (0.83) is wrong because it results from dividing PV by EV (60,000/50,000 = 1.2) or misapplying the formula — 0.83 corresponds to EV/PV (50,000/60,000), which is the Schedule Performance Index (SPI), not CPI. Option B (1.10) is wrong because it results from dividing AC by EV (55,000/50,000 = 1.1), which inverts the CPI formula. Option D (1.20) is wrong because it results from dividing PV by EV (60,000/50,000 = 1.2), which is the inverse of SPI and has no standard EVM meaning.

49
MCQhard

A project manager is developing the project schedule and needs to determine the critical path. The network diagram shows: Task A (3 days) and Task B (5 days) start concurrently. Task C (4 days) depends on both A and B. Task D (2 days) depends on C. Task E (6 days) depends on A only and runs in parallel with C and D. What is the duration of the critical path?

A.11 days
B.15 days
C.14 days
D.9 days
AnswerA

The path A-B-C-D is the longest: A (3) + B (5) + C (4) + D (2) = 14 days. However, since A and B start concurrently, the path through B and C begins after B completes. Wait—actually the critical path is the longest path: A(3) + B(5) + C(4) + D(2) = 14 days. But A and B are concurrent, so the path through A and E is 3+6=9. The path through A, then C, D would be 3+4+2=9, but C depends on B as well, so C cannot start until both A and B finish. Therefore B (5) is the constraint. Path: B(5) + C(4) + D(2) = 11 days. But A must also finish before C starts. A finishes at day 3, B finishes at day 5. C starts at day 5 and ends at day 9. D starts at day 9 and ends at day 11. So critical path is 11 days.

Why this answer

The critical path is the longest sequence of dependent tasks. Task C depends on both A and B, so it cannot start until B finishes at day 5. Task C takes 4 days (ending day 9), and Task D takes 2 days (ending day 11).

The path through E is only 9 days, making the B-C-D path the critical path at 11 days.

Exam trap

The trap here is assuming that Task A's path combined with C and D determines the critical path, when actually Task B's longer duration delays the start of Task C.

50
MCQhard

In a network diagram, Activity A has a duration of 5 days, Activity B has 3 days, and Activity C has 4 days. Activity A and B can start simultaneously, but Activity C cannot start until both A and B are complete. What is the critical path duration?

A.7 days
B.8 days
C.12 days
D.9 days
AnswerD

Activity C depends on both A and B, so its earliest start is the longer of the two parallel paths: A finishes at day 5, B at day 3. Adding C's 4 days gives 9 days, the critical path duration. The A-C sequence governs, not B-C.

Why this answer

The critical path is the longest sequence of dependent activities. Activities A (5 days) and B (3 days) run in parallel, so the earliest they can both finish is day 5 (when A completes). Activity C (4 days) starts after both finish, so it runs from day 5 to day 9.

Thus the total project duration is 5 + 4 = 9 days, making D the correct answer.

Exam trap

PK0-005 often tests whether candidates mistakenly add all durations sequentially or incorrectly use the shorter parallel activity, forgetting that the critical path is the longest path through the network.

How to eliminate wrong answers

Option A (7 days) is wrong because it incorrectly adds B's duration to C (3+4) while ignoring that A must also finish, and A is longer than B. Option B (8 days) is wrong because it likely averages or misadds the parallel durations, perhaps assuming A and B finish at different times but not accounting for the full 5-day wait. Option C (12 days) is wrong because it simply sums all three durations (5+3+4) as if they were sequential, ignoring that A and B can run in parallel.

51
MCQeasy

A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?

A.$50,000
B.$10,000
C.$40,000
D.$25,000
AnswerB

EMV quantifies risk exposure by multiplying monetary impact by probability: $50,000 × 0.20 = $10,000. This figure lets the project manager weigh the risk against mitigation costs, satisfying the stem's requirement for a single expected monetary value.

Why this answer

EMV = Probability × Impact = 20% × $50,000 = $10,000. This is a quantitative risk analysis technique.

52
MCQmedium

A project manager is closing a project that was terminated early because the business case was no longer viable. The sponsor asks what must still be completed before the project can be formally closed. Which of the following should the project manager do?

A.Move directly to the next project phase since the current project has no remaining deliverables to verify.
B.Initiate a change request to revise the project charter so the termination is officially authorized.
C.Perform the Close Project or Phase process, including finalizing all closure documentation and releasing project resources.
D.Conduct a final quality audit on all deliverables produced to date to confirm they meet the original scope.
AnswerC

Even when a project is terminated early, the Close Project or Phase process must still be executed. This includes obtaining final acceptance of any completed deliverables, archiving project documents, documenting the reasons for termination, and releasing team members and other resources. Skipping closure activities leaves the project open and prevents organizational learning.

Why this answer

The Close Project or Phase process is mandatory regardless of whether a project ends through normal completion or early termination. It ensures final acceptance of completed deliverables, proper archiving of project documents, release of resources, and documentation of lessons learned. The termination reason must be recorded to support organizational process assets and future decision-making.

Exam trap

The trap here is assuming that early termination exempts the project manager from performing formal closure activities.

53
MCQmedium

A project manager has just received formal sign-off on the project charter from the sponsor. The project involves a new CRM system for a mid-sized company. What is the most appropriate immediate next step in the project life cycle?

A.Close the project and archive the charter.
B.Begin executing the project work according to the charter.
C.Identify stakeholders and create a stakeholder register.
D.Develop the project management plan.
AnswerD

After the charter is approved, the project enters the Planning process group, where the project management plan is created. This plan integrates scope, schedule, cost, quality, resource, communications, risk, procurement, and stakeholder management plans. It provides the baseline and guidance needed before execution begins. Developing the plan is the logical next step to translate the charter's high-level authorization into actionable details.

Why this answer

Once the project charter is approved, the project moves into the Planning process group. The project management plan is the primary output that integrates all subsidiary plans and baselines. It guides execution, monitoring, and control.

Beginning execution or closing the project without planning would be premature and would violate the standard project life cycle sequence.

Exam trap

The trap here is assuming that charter approval immediately triggers execution, when in fact planning must occur first to create the project management plan.

54
MCQmedium

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

A.Team members feel a sense of closure.
B.Team members work together efficiently.
C.Team members challenge each other's ideas.
D.Team members are polite and avoid conflict.
AnswerC

During storming, disagreements surface as members push competing approaches and question one another's proposals, so challenging each other's ideas is the characteristic behaviour. This precedes norming, where the team settles on shared working agreements and roles.

Why this answer

In Tuckman's model, the storming stage is characterized by conflict and competition as team members assert their ideas, challenge one another, and jockey for roles and influence. Challenging each other's ideas is the hallmark behavior of storming, as the team works through differences in working styles and expectations.

Exam trap

PK0-005 often tests the storming stage by offering 'polite and avoid conflict' as a distractor, which actually describes forming, so candidates must associate conflict and idea-challenging with storming.

How to eliminate wrong answers

Option A is wrong because a sense of closure and reflection on lessons learned occurs in the adjourning stage, when the team disbands. Option B is wrong because working together efficiently and productively describes the performing stage, where the team operates as a cohesive unit. Option D is wrong because politeness and conflict avoidance characterize the forming stage, where members are cautious and orient themselves to the team.

55
MCQmedium

A project manager is planning a system migration with a fixed regulatory deadline. The sponsor asks how the team will know whether the project remains on track to finish by that date without waiting for the final status report. Which planning artifact should the project manager produce to answer this?

A.A responsibility assignment matrix mapping each work package to an owner.
B.A milestone list with the regulatory completion date flagged as a mandatory milestone.
C.A stakeholder engagement assessment matrix recording current and desired engagement levels.
D.A resource calendar showing availability and planned leave for each team member.
AnswerB

A milestone list identifies significant checkpoints, and mandatory milestones are those required by contract or regulation. Flagging the regulatory date lets the team track progress against discrete, zero-duration checkpoints rather than only the final deliverable, so slippage is visible as soon as an intermediate milestone is missed, well before the closing status report is produced.

Why this answer

Mandatory milestones are contractually or regulatorily required checkpoints, and recording them in the milestone list creates discrete go or no-go points. Comparing actual milestone achievement against planned dates gives the sponsor an early, objective indicator of schedule health, independent of narrative status reporting, and it highlights which checkpoint failure would jeopardize the regulatory date.

Exam trap

The trap here is confusing artifacts that assign ownership, track availability, or assess engagement with artifacts that actually measure progress against a deadline.

56
MCQhard

During project execution, a vendor is hired to provide specialized services. The contract is structured so that the vendor is paid for all allowable costs plus a fixed fee. Which type of contract is this?

A.Time and Materials (T&M) contract
B.Lump-sum contract
C.Fixed-price contract
D.Cost-reimbursable contract
AnswerD

Cost-reimbursable contracts pay the vendor all allowable incurred costs plus a fixed fee, matching the stem exactly. The fee is fixed while costs vary, distinguishing it from fixed-price, which sets one total price regardless of actual costs.

Why this answer

A cost-reimbursable contract reimburses the vendor for all allowable incurred costs plus a fee representing vendor profit, which matches the scenario's description of payment for all allowable costs plus a fixed fee. This contract type is used when the scope is uncertain and the buyer bears more cost risk.

Exam trap

PK0-005 often tests contract types by describing the payment structure, so candidates must distinguish 'all allowable costs plus a fixed fee' (CPFF) from T&M (hours plus materials) and fixed-price (lump sum).

How to eliminate wrong answers

Option A is wrong because a Time and Materials (T&M) contract pays for actual hours worked at agreed rates plus materials, not for all allowable costs plus a fixed fee. Option B is wrong because a lump-sum contract, synonymous with fixed-price, pays a single fixed amount regardless of actual costs, placing cost risk on the seller. Option C is wrong because a fixed-price contract sets a predetermined price for the defined scope, which contradicts the cost-reimbursement structure described.

57
MCQeasy

A project manager is initiating a new project and needs to identify the key stakeholders. Which document typically provides the initial list of stakeholders and their roles?

A.Stakeholder register
B.Communications management plan
C.Work breakdown structure (WBS)
D.Project charter
AnswerD

The project charter formally authorizes the project and identifies the initial stakeholders, including the project sponsor, key team members, and other parties with a vested interest. It provides the project manager with the authority to begin work and is a primary input to stakeholder identification. This makes it the correct source for the initial stakeholder list.

Why this answer

The project charter is the document that formally authorizes the project and identifies the initial stakeholders. It is an input to the Identify Stakeholders process, providing the project manager with the authority and the first list of people and organizations affected by the project. The stakeholder register is then created from this information.

Exam trap

The trap here is selecting the stakeholder register, which is a detailed output, instead of the project charter, which is the initiating document that first names key stakeholders.

58
MCQeasy

A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?

A.Project scope statement
B.Project management plan
C.Business case
D.Project charter
AnswerD

The project charter formally authorises the project and names the project manager. It contains the business case, high-level scope and budget constraints, exactly the elements described, distinguishing it from subsidiary documents such as the scope statement.

Why this answer

The project charter is the document that formally authorizes the project, names the project manager, and captures the business case, high-level scope, and budget constraints. It is issued by the sponsor (or PMO) and gives the PM authority to apply organizational resources. This matches the question's description exactly.

Exam trap

PK0-005 often tests the distinction between the charter (authorizes, names PM) and the business case (justifies) or scope statement (details deliverables), catching candidates who pick the document that 'sounds most strategic.'

How to eliminate wrong answers

Option A is wrong because the project scope statement details deliverables, acceptance criteria, and exclusions — it is developed after the charter and does not authorize the project. Option B is wrong because the project management plan is the comprehensive document describing how the project will be executed, monitored, and closed — created after the charter. Option C is wrong because the business case justifies the project economically but does not formally authorize it or assign the PM.

59
MCQhard

A project manager is leading a project to implement a new enterprise resource planning (ERP) system. The project is in the Closing phase. The project manager has verified that all deliverables have been accepted by the customer and all invoices have been paid. However, the project manager realizes that the lessons learned repository has not been updated. Which of the following should the project manager do?

A.Proceed to close the project since all deliverables are accepted and payments are complete.
B.Transfer the remaining project team members to other projects before updating lessons learned.
C.Update the lessons learned repository with the project's successes, challenges, and recommendations.
D.Schedule a meeting with the customer to renegotiate the contract terms.
AnswerC

Updating the lessons learned repository is an essential part of the Closing phase. It documents what went well, what could be improved, and recommendations for future projects. This knowledge transfer is a key output of the Close Project or Phase process. The project manager should complete this before final project closure, regardless of other completion criteria. It ensures organizational learning and continuous improvement.

Why this answer

The Closing phase includes updating the lessons learned repository as a key output. Even if deliverables are accepted and payments made, the project manager must capture and share lessons learned to enable organizational learning. This should be done before releasing the team and formally closing the project.

It is a required step, not optional.

Exam trap

The trap here is assuming that once deliverables are accepted and payments are made, the project can be closed without completing all Closing phase activities, such as updating lessons learned.

60
Multi-Selecthard

A project manager is moving a project from Planning into Executing. The sponsor asks which activities formally mark the transition and enable the team to begin producing deliverables. Which TWO activities should the project manager identify? (Choose two.)

Select 2 answers
A.Conducting a kickoff meeting to communicate the approved plan and align the team.
B.Completing procurement closeout for all vendor contracts signed during planning.
C.Archiving the project charter and lessons learned register to close the planning phase.
D.Obtaining approval of the project management plan from the sponsor and key stakeholders.
E.Submitting a change request to the change control board to authorize execution.
AnswersA, D

The kickoff meeting communicates the approved project management plan, roles, responsibilities, and ground rules to the team and stakeholders, signaling the start of execution. It aligns everyone on objectives and expectations before work begins. In CompTIA Project+ sequencing, the kickoff occurs after plan approval and before or as execution starts, making it one of the activities that formally launches the Executing phase.

Why this answer

The transition from Planning to Executing is marked by approval of the integrated project management plan and the kickoff meeting that communicates it. Approval establishes the baselines the team will execute against, while the kickoff aligns people and expectations. Change requests, archiving, and procurement closeout belong to Monitoring and Controlling or Closing and do not authorize or launch execution.

Exam trap

The trap here is assuming that execution begins when planning tasks simply stop, when in fact it requires explicit plan approval and a kickoff to communicate that approved plan.

61
MCQmedium

A project manager is closing out a project that was terminated early by the sponsor due to shifting business priorities. The deliverables were only partially completed, and several contracts remain open. What should the project manager do FIRST?

A.Immediately release all team members and close all contracts before any documentation.
B.Escalate to the PMO to determine whether the project should be reopened before taking any action.
C.Transfer the remaining deliverables to the operations team without any formal closure activities.
D.Initiate the close project or phase process and document the reason for termination in the final report.
AnswerD

Even when a project is terminated early, the Close Project or Phase process must still be performed. This includes documenting the reason for termination, capturing lessons learned, and formally closing out the project. It ensures organizational knowledge is retained and all administrative closure activities are completed regardless of whether deliverables were finished.

Why this answer

When a project is terminated early, the Close Project or Phase process is still mandatory. The project manager must document the termination reason, capture lessons learned, close open contracts, release resources, and archive project information. Initiating this process first ensures all subsequent closure activities are performed in a structured and documented manner, preserving organizational knowledge.

Exam trap

The trap here is assuming that early termination eliminates the need for formal project closure activities.

62
MCQhard

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000, and the actual cost (AC) is $150,000. What is the estimate to complete (ETC) assuming the project will continue to perform at the same cost efficiency?

A.$100,000
B.$80,000
C.$150,000
D.$120,000
AnswerA

Cost performance index is EV divided by AC, so 120,000 / 150,000 = 0.8. The estimate to complete is (BAC - EV) / CPI, giving 80,000 / 0.8 = $100,000, assuming the same cost efficiency continues.

Why this answer

ETC = (BAC − EV) / CPI. Here CPI = EV/AC = 120,000/150,000 = 0.8. Remaining work = BAC − EV = 200,000 − 120,000 = 80,000.

ETC = 80,000 / 0.8 = $100,000. This assumes the project continues at the same cost efficiency (CPI remains 0.8).

Exam trap

PK0-005 often tests whether candidates apply the correct ETC formula for 'same cost efficiency' — many mistakenly use BAC − EV (ignoring CPI) and pick $80,000.

How to eliminate wrong answers

Option B is wrong because $80,000 is simply BAC − EV (remaining budget at planned rate), ignoring the cost performance index. Option C is wrong because $150,000 is the actual cost to date, not the estimate to complete remaining work. Option D is wrong because $120,000 is the earned value, which measures work performed, not remaining cost.

63
MCQmedium

In a network diagram, if Activity B cannot start until Activity A is complete, what type of dependency is this?

A.Finish-to-Finish (FF)
B.Start-to-Start (SS)
C.Finish-to-Start (FS)
D.Start-to-Finish (SF)
AnswerC

Finish-to-Start (FS) directly encodes the stem's constraint: B's start is gated by A's completion. It is the default precedence relationship in project scheduling, so any successor activity waits on its predecessor's finish. Other dependency types (SS, FF, SF) permit overlap or different anchor points, none of which satisfy "cannot start until complete".

Why this answer

A Finish-to-Start (FS) dependency means the successor activity cannot begin until the predecessor activity has finished. The scenario — Activity B cannot start until Activity A is complete — is the definition of FS, which is also the most common dependency type in project schedules.

Exam trap

PK0-005 often tests the four dependency types by swapping the start/finish terms — candidates must carefully map 'B cannot start until A finishes' to Finish-to-Start, not Start-to-Finish or Finish-to-Finish.

How to eliminate wrong answers

Option A is wrong because Finish-to-Finish (FF) means the successor cannot finish until the predecessor finishes — both end together, not a start-after-finish relationship. Option B is wrong because Start-to-Start (SS) means the successor cannot start until the predecessor starts — they begin together. Option D is wrong because Start-to-Finish (SF) means the successor cannot finish until the predecessor starts, a rarely used dependency typically seen in shift-based or just-in-time scheduling.

64
Multi-Selecthard

A project manager is performing quality control on a software development project. The team has completed coding and is now testing the software. The project manager wants to identify the root cause of defects that are being found during testing. Which TWO tools or techniques should the project manager use? (Choose two.)

Select 2 answers
A.Pareto chart
B.Cause-and-effect diagram
C.Flowchart
D.Scatter diagram
E.Control chart
AnswersA, B

A Pareto chart is a histogram ordered by frequency that helps identify the most significant factors contributing to a problem. In quality control, it is used to prioritize defects by frequency or impact, often following the 80/20 rule. In this scenario, it helps the project manager focus on the few defect types that cause the majority of issues, enabling efficient root cause analysis and corrective action.

Why this answer

The cause-and-effect diagram and Pareto chart are both quality control tools used for root cause analysis. The cause-and-effect diagram helps brainstorm potential causes, while the Pareto chart helps prioritize the most significant causes. Together, they enable the project manager to identify and focus on the root causes of defects.

Exam trap

The trap here is selecting control charts or scatter diagrams, which monitor or show relationships but do not directly identify root causes.

65
MCQhard

A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?

A.5 days
B.7 days
C.4 days
D.0 days
AnswerD

The chain A then B then C gives a single critical path of 5+7+4 days, so no slack exists anywhere along it. Activity B sits on that critical path, meaning any delay slips the project; its total float is therefore zero days.

Why this answer

Activity B is on the critical path: A (5) → B (7) → C (4) = 16 days total, and B has no slack because any delay to B delays C and the project. Total float is calculated as Late Start − Early Start (or Late Finish − Early Finish); for B, both are equal, giving 0 days of float.

Exam trap

PK0-005 often tests whether candidates confuse activity duration with float — the trap is picking the duration of B (7) or another activity instead of computing LS − ES.

How to eliminate wrong answers

Option A is wrong because 5 days is the duration of Activity A, not the float of B. Option B is wrong because 7 days is the duration of Activity B itself, not its float. Option C is wrong because 4 days is the duration of Activity C, not the float of B.

66
MCQeasy

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

A.Accept
B.Avoid
C.Mitigate
D.Transfer
AnswerC

Correct: mitigation reduces probability or impact.

Why this answer

Mitigate is the risk response strategy that focuses on reducing either the likelihood or the impact of a risk. In project management (e.g., PMBOK), mitigation involves proactive actions such as implementing additional testing, using redundant components, or providing training to lower the chance of a risk occurring or to lessen its consequences if it does. This is distinct from other strategies that change the risk's probability/impact by other means, such as avoiding the risk entirely or shifting it to a third party.

Exam trap

PK0-005 often tests the subtle difference between mitigating and avoiding a risk—candidates may pick 'avoid' thinking it means reducing impact, but avoidance removes the risk entirely by changing the plan.

How to eliminate wrong answers

Option A is wrong because acceptance means acknowledging the risk and taking no action unless it occurs, which does not reduce probability or impact. Option B is wrong because avoidance involves changing the project plan to eliminate the risk entirely, not just reducing it. Option D is wrong because transfer shifts the financial impact to a third party (e.g., insurance) but does not reduce the probability or impact itself.

67
Multi-Selecthard

A project manager is leading a project to develop a new mobile application. The project is in the Planning phase. The project manager is identifying and documenting the high-level risks that could affect the project. Which two of the following should the project manager include in the risk register? (Choose two.)

Select 2 answers
A.The project sponsor has approved the project charter.
B.The project budget has been set at $500,000.
C.A potential delay in receiving hardware for the development team due to global supply chain issues.
D.The development team lacks experience with the chosen mobile development framework.
E.The customer has requested a change to the app's color scheme.
AnswersC, D

This is a valid risk because it is an uncertain event that could negatively impact the project schedule. Global supply chain issues are external and can cause delays. Documenting it in the risk register allows the project manager to analyze its probability and impact, and plan responses such as ordering hardware early or identifying alternative suppliers. It is a high-level risk appropriate for the Planning phase.

Why this answer

The risk register documents potential uncertain events that could affect the project. Supply chain delays and lack of team experience are both uncertain future events that could impact the project negatively, so they should be included. Approved charter, set budget, and change requests are not risks; they are facts or formal changes that are managed through other processes.

Exam trap

The trap here is confusing known facts or change requests with risks, which must be uncertain future events that could affect the project.

68
MCQmedium

During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?

A.Conducting lessons learned
B.Archiving project documents
C.Releasing resources
D.Obtaining formal acceptance
AnswerD

Obtaining formal acceptance is the closing activity where the sponsor or customer signs off on the deliverables, confirming they meet requirements. This documented approval is what formally closes the project and satisfies the acceptance criterion in the stem.

Why this answer

Obtaining formal acceptance is the project closing activity in which the sponsor or customer formally signs off on the deliverables, confirming they meet requirements and bringing the project to an authorized close. This typically involves a formal acceptance document, sign-off, or completion certificate. It is the activity specifically tied to gaining stakeholder approval of deliverables.

Exam trap

PK0-005 often tests the order and purpose of closing activities — candidates pick lessons learned or archiving because they are closing tasks, but only formal acceptance obtains sponsor or customer sign-off on deliverables.

How to eliminate wrong answers

Option A is wrong because conducting lessons learned captures process improvements and knowledge for future projects; it does not obtain deliverable acceptance. Option B is wrong because archiving project documents is a records-management activity that preserves artifacts after closure, not a sign-off step. Option C is wrong because releasing resources is an administrative closure task that frees team members and assets, and it happens after or alongside acceptance, not as the acceptance mechanism itself.

69
MCQmedium

During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?

A.Scope statement
B.Project charter
C.Work breakdown structure (WBS)
D.Network diagram
AnswerC

Decomposing project scope into smaller, manageable components produces the work breakdown structure, a hierarchical deliverable-oriented decomposition of total scope. It forms the foundation for estimating, scheduling and control, directly satisfying the planning activity described in the stem.

Why this answer

The Work Breakdown Structure (WBS) is the deliverable-oriented hierarchical decomposition of the total scope of work required to complete the project. It breaks the project into smaller, more manageable components called work packages, which can be estimated, scheduled, and assigned.

Exam trap

PK0-005 often tests the confusion between scope-related documents, so candidates must distinguish the WBS (decomposition) from the scope statement (narrative description) and the charter (authorization).

How to eliminate wrong answers

Option A is wrong because the scope statement is a narrative description of the project scope, deliverables, and boundaries—it does not decompose work into components. Option B is wrong because the project charter authorizes the project at a high level and is created during initiating, not planning. Option D is wrong because a network diagram is a scheduling tool that shows activity dependencies, not a scope decomposition document.

70
Multi-Selectmedium

A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)

Select 2 answers
A.Develop the risk register
B.Obtain formal acceptance from the sponsor
C.Conduct feasibility study
D.Create the project charter
E.Archive project documents
AnswersB, E

Obtaining formal acceptance from the sponsor satisfies the closure requirement to confirm deliverables meet agreed criteria before releasing resources. This sign-off transfers ownership to the business and authorises final payments, distinguishing closure from ongoing monitoring. Without documented sponsor acceptance, the project cannot be formally closed or lessons learned validated.

Why this answer

Option B is correct because obtaining formal acceptance from the sponsor is a key project closure activity; the sponsor (or customer) must formally sign off that deliverables meet requirements, which is required before the project can be officially closed. Option E is correct because archiving project documents is part of closing the project; lessons learned, final reports, and project records are collected, indexed, and stored for future reference and organizational process assets. Option A is incorrect because the risk register is developed during project planning and updated throughout execution, not created at closure.

Option C is incorrect because a feasibility study is performed during the pre-project or initiation phase to determine whether the project is viable. Option D is incorrect because the project charter is created during initiation to formally authorize the project, not during closure.

Exam trap

PK0-005 often tests the distinction between process groups; the trap is selecting planning or initiating activities (risk register, charter, feasibility study) as closure activities because they are familiar project documents.

71
MCQeasy

Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?

A.Project management plan
B.Project charter
C.Project scope statement
D.Work breakdown structure
AnswerB

The project charter is the document that formally authorises the project's existence and grants the project manager authority to apply organisational resources to its activities. It names the project manager, states objectives and defines constraints, satisfying the requirement for formal authorisation and resource authority.

Why this answer

The project charter is the document that formally authorizes a project and gives the project manager authority to apply organizational resources. It is typically issued by the project sponsor or initiating entity and marks the official start of the project.

Exam trap

PK0-005 often tests the distinction between the project charter and the project management plan, as both are foundational documents but serve different purposes.

How to eliminate wrong answers

Option A is wrong because the project management plan describes how the project will be executed, monitored, and controlled, but it does not authorize the project. Option C is wrong because the project scope statement details the project deliverables and boundaries, but it is not the authorizing document. Option D is wrong because the work breakdown structure is a deliverable-oriented decomposition of the project scope, not an authorization document.

72
Multi-Selectmedium

During the planning phase, which three documents are typically created? (Select THREE.)

Select 3 answers
A.Risk register
B.Work Breakdown Structure
C.Project charter
D.Schedule baseline
E.Lessons learned
AnswersA, B, D

The risk register records identified risks, their probability, impact, and planned responses. It is compiled during planning as threats and opportunities are assessed, satisfying the stem's requirement for a planning-phase document that supports ongoing monitoring and response throughout execution.

Why this answer

The Risk register (A) is a planning-phase artifact because it is created during risk planning to identify, analyze, and document risks along with their probability, impact, and responses. The Work Breakdown Structure (B) is produced in planning when the project scope is decomposed into deliverables and work packages, forming the basis for estimating and scheduling. The Schedule baseline (D) is also a planning output, established once the schedule is developed and approved, and it is used to measure schedule performance.

The Project charter (C) is not a planning document because it is created and approved during the initiating phase, before planning begins. Lessons learned (E) is not a planning document because it is compiled throughout the project and finalized during closing, not typically created as a planning-phase output.

Exam trap

PK0-005 often tests the phase in which key documents are created, and candidates may confuse planning outputs with initiation or execution outputs.

73
MCQhard

A project manager is reviewing the procurement process. Which document is used to invite vendors to submit a proposal for a project?

A.Request for Information (RFI)
B.Statement of Work (SOW)
C.Request for Proposal (RFP)
D.Request for Quotation (RFQ)
AnswerC

An RFP formally solicits vendor proposals by stating requirements, evaluation criteria and submission terms, letting the buyer compare competing bids. It fits the stem's procurement step of inviting proposals, unlike an RFI, which only gathers capability information before requirements are fixed.

Why this answer

A Request for Proposal (RFP) is used to solicit proposals from vendors.

74
MCQhard

A project team is decomposing the project scope into work packages. Which of the following best describes the purpose of a Work Breakdown Structure (WBS)?

A.To provide a hierarchical representation of all work required to complete the project deliverables
B.To list all project risks and their responses
C.To identify the critical path of the project schedule
D.To define the communication channels among stakeholders
AnswerA

The WBS decomposes the total project scope into progressively smaller, manageable work packages, giving a hierarchical view of every deliverable and its associated work. This directly satisfies the need to break scope down into work packages for planning and control.

Why this answer

A Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the total scope of work required to complete the project. It breaks the project down from the final deliverable into progressively smaller, more manageable components called work packages. This provides the foundation for estimating, scheduling, and assigning responsibility.

Exam trap

PK0-005 often tests the confusion between the WBS and the schedule or risk register; candidates must remember that the WBS is strictly about scope decomposition, not timing, risk, or communication.

How to eliminate wrong answers

Option B is wrong because risk identification and response planning are outputs of the Risk Management processes (Identify Risks, Plan Risk Responses), not the WBS. Option C is wrong because the critical path is determined through schedule network analysis techniques such as the Critical Path Method (CPM), which uses activity durations and dependencies, not the WBS hierarchy. Option D is wrong because communication channels are defined in the Communications Management Plan, which is a separate project management artifact.

75
Multi-Selectmedium

A project manager is closing a project. Which TWO activities are typically performed during the closing phase?

Select 2 answers
A.Performing earned value analysis
B.Creating the risk register
C.Obtaining formal acceptance from the sponsor
D.Archiving project documents
E.Developing the project charter
AnswersC, D

Closing requires the sponsor to formally accept the delivered product, confirming it meets requirements before the project can be authorised for closure. This sign-off satisfies the stem's closing-phase constraint, since acceptance occurs after verification and precedes final handover and resource release.

Why this answer

Option C (Obtaining formal acceptance from the sponsor) is correct because the closing phase requires verifying that deliverables meet requirements and securing the sponsor's sign-off, which formally confirms project completion and triggers final payments or handover. Option D (Archiving project documents) is correct because closing includes collecting, indexing, and storing project records, lessons learned, and final reports in the organizational knowledge repository for future reference and audits. Option A (Performing earned value analysis) belongs to monitoring and controlling, where EVM metrics like CPI and SPI are calculated during execution, not at closure.

Option B (Creating the risk register) is a planning activity performed in risk management before execution begins. Option E (Developing the project charter) is an initiating process that formally authorizes the project, so it occurs before any closing work.

Page 1 of 3 · 188 questions totalNext →

Ready to test yourself?

Try a timed practice session using only Pkp Project Lifecycle questions.