20+ practice questions focused on Project Life Cycle — one of the most tested topics on the CompTIA Project+ PK0-005 exam. Each question includes a detailed explanation so you learn why the right answer is correct.
Start Project Life Cycle PracticeA project manager is calculating the Expected Monetary Value (EMV) for a risk event. The probability of the risk occurring is 20%, and the impact if it occurs is $50,000. What is the EMV?
Explanation: EMV = Probability × Impact = 0.20 × $50,000 = $10,000. This represents the expected cost of the risk event. The EMV is positive when considering the magnitude of potential loss, though in risk management it may be expressed as a negative value for threats. The calculation yields $10,000.
A project manager is identifying response strategies for a risk that could impact the project schedule. Which TWO options are risk response strategies? (Select TWO.)
Explanation: The standard risk response strategies for threats include avoid, transfer, mitigate, accept, and escalate. For opportunities, the strategies include exploit, enhance, share, accept, and escalate. In this case, 'Transfer' and 'Avoid' are both valid threat response strategies. 'Enhance' is for opportunities only, 'Ignore' is not a recognized strategy, and 'Escalate' is a standard strategy, but the question requires selecting exactly two, and Transfer and Avoid are correct.
A project manager is reviewing the risk register and notices a risk with a high probability (0.7) and high impact ($50,000). The team decides to purchase insurance to cover the potential loss. Which TWO risk response strategies are being applied?
Explanation: Purchasing insurance transfers the financial risk to the insurance company, which is a classic example of risk transfer (Transfer strategy). Mitigation involves actions to reduce the probability or impact of a risk, but insurance does not reduce probability or impact; it only shifts the financial burden. Therefore, only Transfer is correctly applied in this scenario. The question asks for two strategies, but only one strategy is demonstrated; the other strategy is not represented among the options.
A project manager is analyzing the network diagram for a project. The critical path is A-B-C, with durations 3, 4, 2 days respectively. Activity D (2 days) has a finish-to-start relationship with A and a start-to-start relationship with B. Which TWO statements are correct about the schedule?
Explanation: The critical path A-B-C has duration 3+4+2=9 days, so statement B is correct. Activity D has total float of 4 days (LS-ES = 7-3=4), so statement D is correct. Statement A is essentially a restatement of option D and thus not considered a separate correct statement for this two-statement question.
During which project phase is the project charter typically created and approved?
Explanation: The project charter is created during the Initiating phase to formally authorize the project.
+15 more Project Life Cycle questions available
Practice all Project Life Cycle questions1. Baseline your knowledge
Start with 10 questions to gauge your current understanding of Project Life Cycle. This tells you whether you need a concept refresher or just practice.
2. Review every explanation
For each question — right or wrong — read the full explanation. Understanding why an answer is correct is more valuable than knowing the answer itself.
3. Focus on exam traps
Project Life Cycle questions on the PK0-005 frequently use trap wording. Look for subtle differences in answers that test your precision, not just general knowledge.
4. Reach 80% consistently
Do repeated sessions until you score 80%+ three times in a row. Then move to mixed-mode practice to test cross-topic recall under realistic conditions.
The exact number varies per candidate. Project Life Cycle is tested as part of the CompTIA Project+ PK0-005 blueprint. Practicing with targeted Project Life Cycle questions ensures you can handle any format or difficulty that appears.
Yes. Courseiva provides free PK0-005 practice questions across all exam topics and domains. The platform includes topic-based practice, mock exams, missed-question review, bookmarked questions, and readiness tracking — no account required.
Difficulty is subjective, but Project Life Cycle is a high-priority exam concept tested in multiple ways — direct recall, scenario analysis, and command-output interpretation. Consistent practice is the best way to build confidence.
Launch a full Project Life Cycle practice session with instant scoring and detailed explanations.
Start Project Life Cycle Practice →