Courseiva
Project Life CyclehardMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is analyzing the network diagram and identifies that Activity X has a late start (LS) of day 10 and an early start (ES) of day 8. Which TWO statements are true about Activity X? (Select two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The activity can be delayed by up to 2 days without affecting the project completion date.

Total float = LS - ES = 10-8 = 2 days. It is not on the critical path because critical path activities have zero float.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The activity is on the critical path.

    Why it's wrong here

    Critical path has zero float.

  • The activity can be delayed by up to 2 days without affecting the project completion date.

    Why this is correct

    Total float is the allowable delay.

  • The total float is -2 days.

    Why it's wrong here

    Float cannot be negative if LS > ES.

  • The activity has free float of 2 days.

    Why it's wrong here

    Free float may differ; total float is 2.

  • The total float is 2 days.

    Why this is correct

    Total float = LS - ES = 2.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.