Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

Which document is used to formally accept the project deliverables and signify project closure?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Formal acceptance

Formal acceptance from the sponsor or customer is a key closing activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why it's wrong here

    The charter authorizes the project.

  • Scope statement

    Why it's wrong here

    The scope statement defines what is included.

  • Formal acceptance

    Why this is correct

    Formal acceptance documents sign-off.

  • Lessons learned

    Why it's wrong here

    Lessons learned capture knowledge.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.