PK0-005 Project Life Cycle Practice Question
Which document is used to formally accept the project deliverables and signify project closure?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Formal acceptance
Formal acceptance from the sponsor or customer is a key closing activity.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project charter
Why it's wrong here
The charter authorizes the project.
- ✗
Scope statement
Why it's wrong here
The scope statement defines what is included.
- ✓
Formal acceptance
Why this is correct
Formal acceptance documents sign-off.
- ✗
Lessons learned
Why it's wrong here
Lessons learned capture knowledge.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.