CCNA Pkp Project Lifecycle Questions

75 of 165 questions · Page 2/3 · Pkp Project Lifecycle topic · Answers revealed

76
MCQhard

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

A.The project is over budget and behind schedule.
B.The project is under budget and ahead of schedule.
C.The project is over budget and ahead of schedule.
D.The project is under budget and behind schedule.
AnswerD

CPI=1.2 (>1) under budget; SPI=0.9 (<1) behind schedule.

Why this answer

CPI > 1 means under budget; SPI < 1 means behind schedule.

77
MCQeasy

Which of the following is an example of a risk response strategy to avoid a risk?

A.Changing the project scope to eliminate the risk
B.Accepting the risk and budgeting for impact
C.Purchasing insurance
D.Assigning a risk owner
AnswerA

Scope change to eliminate the risk is avoidance.

Why this answer

Avoidance involves changing the project plan to eliminate the risk or protect objectives.

78
MCQeasy

During which project phase is the project charter created and the project manager formally assigned?

A.Planning
B.Closing
C.Executing
D.Initiating
AnswerD

The project charter is developed during Initiating to authorize the project.

Why this answer

The project charter is created during the Initiating phase, along with assigning the project manager and obtaining authorization.

79
MCQeasy

During which project phase is the project charter typically created and approved?

A.Initiating
B.Closing
C.Executing
D.Planning
AnswerA

The charter is created in the Initiating phase to authorize the project.

Why this answer

The project charter is created during the Initiating phase to formally authorize the project.

80
MCQmedium

According to Tuckman's model, during which stage do team members begin to resolve conflicts and establish norms?

A.Performing
B.Norming
C.Storming
D.Forming
AnswerB

Norming involves establishing consensus and ground rules.

Why this answer

Norming is when team members start to resolve differences and agree on norms.

81
MCQmedium

A project manager is using a risk probability and impact matrix. A risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

A.$15,000
B.$50,000
C.$1,500
D.$150,000
AnswerA

Correct calculation.

Why this answer

EMV = Probability × Impact = 0.3 × $50,000 = $15,000.

82
MCQmedium

During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?

A.Network diagram; activity
B.Work breakdown structure (WBS); work package
C.Project charter; work item
D.Risk register; risk event
AnswerB

The WBS is decomposed into work packages at the lowest level.

Why this answer

The WBS is created, and the lowest level is a work package.

83
Multi-Selecthard

During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?

Select 3 answers
A.Ignore
B.Mitigate
C.Avoid
D.Enhance
E.Transfer
AnswersB, C, E

Mitigation reduces probability or impact.

Why this answer

Risk response strategies include avoid, transfer, mitigate, and accept. Exploit is a positive risk response strategy.

84
MCQeasy

Which cost estimation technique uses historical data from similar projects to estimate the cost of the current project?

A.Parametric estimating
B.Bottom-up estimating
C.Three-point estimating
D.Analogous estimating
AnswerD

Analogous estimating uses historical data from similar projects.

Why this answer

Analogous estimation uses historical data from similar projects as a basis for estimation.

85
MCQeasy

A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?

A.Team members challenge each other's ideas
B.Team members are polite and avoid conflict
C.Team members work together efficiently
D.Team members focus on completing tasks
AnswerA

Storming is characterized by conflict and competition.

Why this answer

In the storming stage, team members may have conflicts and disagreements as they assert their opinions and struggle for positions. This is a natural part of team development.

86
MCQeasy

Which of the following is a common response strategy for negative risks (threats) that involves reducing the probability or impact of the risk?

A.Accept
B.Transfer
C.Mitigate
D.Avoid
AnswerC

Mitigation reduces probability or impact.

Why this answer

Mitigation reduces the probability or impact of a threat.

87
MCQmedium

A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?

A.Low power, low interest
B.Low power, high interest
C.High power, high interest
D.High power, low interest
AnswerC

These stakeholders require the most attention and should be managed closely.

Why this answer

Stakeholders with high power and high interest should be managed closely as they have significant influence and are highly interested in the project's outcome.

88
MCQeasy

Which contract type places the most cost risk on the seller?

A.Cost-reimbursable
B.Fixed-price
C.Time and materials (T&M)
D.Cost-plus-fixed-fee
AnswerB

Correct: Seller bears cost risk.

Why this answer

In a fixed-price contract, the seller bears the risk of cost overruns because the price is set regardless of actual costs.

89
MCQmedium

During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?

A.Change control board
B.Functional manager
C.Project sponsor
D.Project manager
AnswerA

CCB is responsible for approving or rejecting changes.

Why this answer

The change control board (CCB) reviews and approves change requests.

90
MCQhard

During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?

A.Norming
B.Performing
C.Forming
D.Storming
AnswerD

Storming involves conflict and challenges to leadership.

Why this answer

Storming is characterized by conflict and questioning of authority.

91
MCQmedium

A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?

A.Monitor
B.Keep informed
C.Keep satisfied
D.Manage closely
AnswerD

High power and high interest require close management.

Why this answer

Stakeholders with high power and high interest should be managed closely as key players.

92
MCQhard

During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?

A.Decomposition
B.Rolling wave planning
C.Analogous estimating
D.Precedence diagramming
AnswerA

Decomposition is the correct term for breaking down deliverables into work packages.

Why this answer

Decomposition is the process of breaking down deliverables into smaller work packages within the WBS.

93
MCQmedium

A project manager identifies a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

A.$150,000
B.$35,000
C.$50,000
D.$15,000
AnswerD

EMV = 0.30 × 50000 = 15000.

Why this answer

EMV = Probability × Impact = 0.30 × $50,000 = $15,000.

94
MCQhard

A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?

A.0 days
B.1 day
C.2 days
D.5 days
AnswerA

Critical path activities have zero float.

Why this answer

The critical path is A-C-E-F: 5+4+6+1=16 days. The path A-B-D-F: 5+3+2+1=11 days. The float for C is the difference between early start and late start.

Since C is on the critical path, its total float is 0.

95
MCQmedium

A project manager is estimating costs for a new software development project. The company has completed three similar projects in the past. Which cost estimation technique is most appropriate in this scenario?

A.Analogous estimation
B.Bottom-up estimation
C.Parametric estimation
D.Three-point estimation
AnswerA

Analogous uses historical data from similar projects, appropriate here.

Why this answer

Analogous estimation uses historical data from similar projects to estimate costs. It is quick and reliable when past projects are similar. Parametric uses statistical relationships, and bottom-up is detailed and time-consuming.

96
MCQmedium

A project manager is developing a communication plan. Which of the following should be determined first?

A.The communication methods to be used
B.The project's communication budget
C.The stakeholder communication needs
D.The frequency of status reports
AnswerC

Needs should be identified first to tailor the plan.

Why this answer

The first step in communication planning is to identify stakeholder communication needs, including what information they need, when, and how. This ensures that the plan addresses all requirements.

97
MCQhard

During the executing phase, a vendor delivers a product that does not meet the specifications outlined in the SOW. Which document should the project manager reference first to address this issue?

A.Procurement contract
B.Risk register
C.Statement of Work (SOW)
D.Project charter
AnswerC

The SOW specifies the deliverables and acceptance criteria.

Why this answer

The SOW (Statement of Work) defines the deliverables, specifications, and performance criteria. It is the primary reference to verify compliance. The contract includes legal terms but the SOW details the technical requirements.

98
Multi-Selectmedium

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)

Select 2 answers
A.The project is on schedule and on budget
B.The project is ahead of schedule
C.The project is under budget
D.The project is behind schedule
E.The project is over budget
AnswersB, E

Correct: SPI=1.2 > 1 indicates ahead of schedule.

Why this answer

CPI < 1 means over budget; SPI > 1 means ahead of schedule. EAC > BAC typically when CPI < 1, and TCPI to meet BAC is >1.

99
Multi-Selectmedium

During project closing, which THREE activities should be performed?

Select 3 answers
A.Obtain formal acceptance from the sponsor
B.Perform resource leveling
C.Archive project documents
D.Conduct lessons learned
E.Identify risks
AnswersA, C, D

Part of project closing.

Why this answer

Closing includes formal acceptance, lessons learned, and archiving documents. Resource leveling occurs during planning/execution; risk identification occurs during planning.

100
MCQhard

A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?

A.$220,000
B.$250,000
C.$200,000
D.$266,667
AnswerD

EAC = BAC/CPI = 200,000 / 0.75 = 266,667.

Why this answer

CPI = EV/AC = 60,000/80,000 = 0.75. EAC = BAC/CPI = 200,000/0.75 = $266,667.

101
MCQeasy

Which document contains all identified risks, their probability and impact, and planned response strategies?

A.Change log
B.Issue log
C.Project charter
D.Risk register
AnswerD

Correct: The risk register contains risk details.

Why this answer

The risk register is the central repository for risk information throughout the project.

102
Multi-Selecthard

A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)

Select 2 answers
A.Vendor performance
B.Communication needs
C.Budget constraints
D.Risk tolerance
E.Preferred frequency
AnswersB, E

Understanding what information stakeholders need is essential.

Why this answer

Communication needs and preferred frequency are key inputs to the communication plan.

103
MCQeasy

A project manager receives a change request from a stakeholder. What is the first step the project manager should take?

A.Submit the change to the change control board
B.Perform an impact analysis
C.Implement the change immediately
D.Update the project baseline
AnswerB

Impact analysis is the first step in change control.

Why this answer

The first step is to perform an impact analysis to assess the effects of the change before submission to the CCB.

104
MCQmedium

A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?

A.Manage closely with frequent detailed reports.
B.Keep informed with regular status reports.
C.Keep satisfied with periodic high-level updates.
D.Monitor with minimal communication.
AnswerC

Correct: Keep satisfied with minimal but sufficient info.

Why this answer

Stakeholders with high power and low interest should be kept satisfied. They need sufficient information to ensure satisfaction but not overwhelmed with details.

105
Multi-Selectmedium

A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)

Select 2 answers
A.The project is over budget.
B.The project is under budget.
C.The project is getting $1.20 worth of work for every $1 spent.
D.The project is getting $0.83 worth of work for every $1 spent.
E.The project is on schedule.
AnswersA, D

Correct. CPI < 1 means over budget.

Why this answer

CPI = EV/AC = 50000/60000 = 0.83. A CPI less than 1 indicates the project is over budget. The project is spending more than planned for the work performed.

106
Multi-Selectmedium

A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)

Select 2 answers
A.Ensure each element is a deliverable
B.Decompose to work packages
C.Assign durations to elements
D.Include project activities
E.Include only high-level scope
AnswersA, B

WBS focuses on deliverables.

Why this answer

The WBS should be decomposed to work packages, and each element should represent a deliverable, not an activity.

107
MCQmedium

A project has an EV of $40,000, PV of $50,000, and AC of $45,000. What is the cost performance index (CPI)?

A.1.25
B.0.80
C.0.89
D.1.11
AnswerC

Correct: CPI = EV/AC = 40000/45000 = 0.89.

Why this answer

CPI = EV/AC = $40,000/$45,000 = 0.89.

108
MCQmedium

A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?

A.Reject the change request
B.Escalate to the sponsor
C.Implement the change and update baselines
D.Conduct another impact analysis
AnswerC

Approved changes must be integrated into the project.

Why this answer

After approval, the project manager must implement the change, which includes updating all relevant baselines (scope, schedule, cost) and communicating the change to stakeholders.

109
MCQeasy

In a power/interest grid, stakeholders with high power and low interest should be managed with which approach?

A.Keep informed
B.Keep satisfied
C.Monitor
D.Manage closely
AnswerB

Keep satisfied is appropriate for high power, low interest stakeholders.

Why this answer

Stakeholders with high power but low interest need to be kept satisfied to maintain their support without overwhelming them with information.

110
MCQmedium

A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?

A.Document the change in the lessons learned
B.Implement the change and update the project baselines
C.Reject the change and inform the requester
D.Update the risk register
AnswerB

Correct: Approved changes are implemented and baselines updated.

Why this answer

After approval, the change must be implemented and project baselines (scope, schedule, cost) updated to reflect the approved change.

111
MCQmedium

A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?

A.3 days
B.0 days
C.12 days
D.4 days
AnswerB

Critical path activities have zero float.

Why this answer

Activities on the critical path have zero float by definition.

112
Multi-Selecteasy

A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?

Select 3 answers
A.Actual start and end dates
B.Approved start and end dates for activities
C.Activity dependencies
D.Resource assignments
E.Milestones
AnswersB, C, E

Part of the baseline.

Why this answer

The schedule baseline includes the approved start and end dates, milestones, and activity dependencies. It is not updated with changes until approved.

113
MCQmedium

During risk management, a team identifies a risk with a 20% probability of occurrence and a potential cost impact of $50,000. What is the Expected Monetary Value (EMV) of this risk?

A.$10,000
B.$50,000
C.$40,000
D.$20,000
AnswerA

Correct calculation.

Why this answer

EMV = Probability × Impact = 0.20 × $50,000 = $10,000. EMV is used to quantify risks in monetary terms.

114
MCQhard

A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?

A.1.09
B.0.91
C.1.10
D.1.20
AnswerA

CPI = EV/AC = 1.09.

Why this answer

CPI = EV / AC = $120,000 / $110,000 = 1.09.

115
MCQmedium

During project closing, which of the following is the primary purpose of the lessons learned document?

A.To document the project's financial performance
B.To formally accept the project deliverables
C.To provide information for future projects
D.To release project resources
AnswerC

Lessons learned are used to improve future project performance.

Why this answer

Lessons learned capture knowledge and experience from the project to improve future projects. While they may inform the final report, their main value is for continuous improvement.

116
MCQmedium

A project manager is estimating the cost of a new software development project. The project is similar to a previous project that cost $500,000. The PM adjusts for size and complexity and estimates the new project will cost $600,000. Which estimation technique is being used?

A.Parametric estimation
B.Analogous estimation
C.Bottom-up estimation
D.Three-point estimation
AnswerB

Correct: Analogous uses similar past projects.

Why this answer

Analogous estimation uses historical data from similar projects to estimate current project costs, adjusting for differences.

117
MCQmedium

Which of the following is a key input to the change control process when a change request is submitted?

A.Final project report
B.Lessons learned
C.Impact analysis
D.Performance measurement baseline
AnswerC

Impact analysis assesses the effects of the change before approval.

Why this answer

When a change request is submitted, an impact analysis is performed to evaluate the effects on scope, schedule, cost, and quality. This analysis is then presented to the Change Control Board for decision.

118
MCQhard

A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?

A.0.83; over budget
B.1.20; under budget
C.0.83; on budget
D.0.91; under budget
AnswerA

Correct: CPI = 0.83, less than 1 means over budget.

Why this answer

CPI = EV/AC = 50,000/60,000 = 0.83. A CPI less than 1 indicates the project is over budget.

119
MCQhard

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?

A.CPI = 1.10; project is on budget
B.CPI = 1.09; project is under budget
C.CPI = 0.83; project is over budget
D.CPI = 0.91; project is over budget
AnswerD

Correct: CPI < 1 means over budget.

Why this answer

CPI = EV/AC = 50000/55000 ≈ 0.91. A CPI less than 1 indicates the project is over budget.

120
MCQmedium

A project manager is developing the project charter. Which of the following should be included as a key element in the charter to define the project's boundaries?

A.Risk register
B.Detailed work breakdown structure
C.High-level scope
D.Communication plan
AnswerC

High-level scope is a key element of the project charter that defines boundaries.

Why this answer

The project charter includes high-level scope, which defines the boundaries of the project. Assumptions and constraints are also included, but the high-level scope specifically sets the boundaries.

121
MCQhard

A project manager is calculating the critical path. The network diagram shows two paths: Path A: A(3 days) → B(4 days) → C(2 days) = 9 days; Path B: D(5 days) → E(1 day) → F(3 days) = 9 days. Both have total float of zero. What is the total float for an activity on Path A?

A.1 day
B.3 days
C.0 days
D.2 days
AnswerC

Critical path activities have zero float.

Why this answer

On a critical path, all activities have zero total float.

122
MCQhard

A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?

A.8.0 days
B.8.33 days
C.7.5 days
D.9.0 days
AnswerB

Correct PERT calculation.

Why this answer

PERT expected duration = (Optimistic + 4*Most Likely + Pessimistic) / 6 = (5 + 4*8 + 13)/6 = (5+32+13)/6 = 50/6 ≈ 8.33 days.

123
MCQhard

In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?

A.Day 6
B.Day 5
C.Day 7
D.Day 8
AnswerA

Correct: A finishes day 3, B starts day 4, C starts 2 days after B start = day 6.

Why this answer

Activity A finishes at day 3. Activity B starts at day 4 (FS+1? Actually FS means B starts after A finishes, so B starts day 4). With SS+2 lag, C can start 2 days after B starts, i.e., day 6.

124
Multi-Selecthard

A project has a budget at completion (BAC) of $200,000. After two months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. The CPI is 0.89. Which THREE statements are correct regarding cost performance and forecasting?

Select 3 answers
A.The estimate at completion (EAC) is approximately $224,719.
B.The to-complete performance index (TCPI) based on BAC is 1.12.
C.The project is over budget.
D.The variance at completion (VAC) is approximately -$24,719.
E.The project is under budget.
AnswersA, C, D

Correct. EAC = BAC/CPI ≈ $224,719.

Why this answer

CPI = EV/AC = 80/90 = 0.89. The project is over budget. EAC = BAC/CPI = 200,000/0.89 ≈ $224,719.

VAC = BAC - EAC = 200,000 - 224,719 = -$24,719 (overrun).

125
MCQmedium

A project manager is evaluating a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

A.$150,000
B.$1,500
C.$50,000
D.$15,000
AnswerD

EMV = 0.30 × 50,000 = 15,000.

Why this answer

EMV = Probability × Impact = 0.30 × $50,000 = $15,000.

126
Multi-Selectmedium

A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?

Select 2 answers
A.Team members are polite and avoid conflict.
B.Disagreements and competition among team members arise.
C.Team members work together efficiently and effectively.
D.Team members establish norms and ground rules.
E.Team members may challenge the project manager's authority.
AnswersB, E

Correct: Storming involves disagreements and competition.

Why this answer

Storming is characterized by conflict, competition, and challenges to authority as team members express differing opinions.

127
Multi-Selectmedium

During project executing, the team is developing a communication plan. Which THREE factors should the project manager consider when determining the communication needs of stakeholders?

Select 3 answers
A.The project manager's preferred communication style
B.The method of communication (e.g., email, meetings)
C.Stakeholder power/interest level
D.The frequency of communication required
E.The number of project team members
AnswersB, C, D

Correct. The method is essential to ensure effective communication.

Why this answer

A communication plan considers stakeholder information needs, including their required information, preferred frequency, and method of communication. Organizational culture and project complexity are also relevant.

128
Multi-Selecteasy

During project closing, which TWO activities are typically performed?

Select 2 answers
A.Update the risk register
B.Create the project charter
C.Archive project documents
D.Develop the WBS
E.Obtain formal acceptance from the sponsor
AnswersC, E

Correct: archiving is part of closing.

Why this answer

Project closing includes formal acceptance from the sponsor and archiving project documents. Releasing resources is also part of closing, but it's one of the two correct answers here.

129
MCQmedium

During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?

A.Lessons learned
B.Formal acceptance
C.Archiving project documents
D.Final project report
AnswerB

Formal acceptance confirms deliverables are accepted.

Why this answer

Formal acceptance is obtained from the customer or sponsor during closing, often via a project acceptance form.

130
MCQeasy

Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?

A.Executing
B.Closing
C.Planning
D.Initiating
AnswerB

Closing includes formal acceptance, lessons learned, and archiving.

Why this answer

Closing includes formal acceptance, lessons learned, and archiving project documents.

131
MCQmedium

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

A.Team members disengage as the project ends.
B.Team members are polite and avoid conflict.
C.Team members work collaboratively and efficiently.
D.Team members question the project manager's authority and disagree on tasks.
AnswerD

Correct: Storming involves conflict and questioning.

Why this answer

In the storming stage, team members may challenge each other and the project manager, leading to conflicts as they establish roles.

132
MCQmedium

A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?

A.Accept
B.Avoid
C.Transfer
D.Mitigate
AnswerD

Cross-training reduces the impact of losing a team member.

Why this answer

Mitigation reduces the probability or impact of a risk. Cross-training reduces impact.

133
MCQmedium

In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?

A.-$10,000
B.$10,000
C.-$5,000
D.$5,000
AnswerC

CV = EV - AC = 50k - 55k = -5k.

Why this answer

CV = EV - AC = $50,000 - $55,000 = -$5,000, indicating the project is over budget.

134
Multi-Selecthard

A project manager is assigning resources to activities. Activity X requires a specialized skill that is only available from a contractor. The project manager decides to hire the contractor. Which TWO documents are most likely to be used to define the work and terms for this contractor? (Select TWO).

Select 2 answers
A.Statement of Work (SOW)
B.Project charter
C.Work Breakdown Structure (WBS)
D.Request for Proposal (RFP)
E.Procurement contract
AnswersA, E

The SOW describes the work to be performed.

Why this answer

The SOW defines the work to be performed, and the contract defines the legal terms and conditions. The RFP is used to solicit bids, and the WBS is a planning tool, not a procurement document. The project charter authorizes the project.

135
Multi-Selectmedium

A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)

Select 2 answers
A.Frequency of communication
B.Risk register
C.Project charter
D.Stakeholder communication needs
E.Work breakdown structure
AnswersA, D

Frequency is a key component.

Why this answer

A communication plan should include stakeholder communication needs and frequency, as well as the method of communication.

136
Multi-Selecteasy

A project team is in the Performing stage of Tuckman's model. Which TWO behaviors are characteristic of this stage?

Select 2 answers
A.The team focuses on achieving project goals.
B.The team is self-organizing and works interdependently.
C.Team members are polite but unsure of their roles.
D.Team members resolve conflicts openly and constructively.
E.Team members are independent and rely on the project manager for guidance.
AnswersA, B

Correct. In Performing, the team is goal-oriented and efficient.

Why this answer

In the Performing stage, the team is functioning effectively, with established trust and processes. Interdependence and focus on goals are key characteristics.

137
MCQmedium

A project manager is decomposing the project scope into smaller components. Which output is produced?

A.Risk breakdown structure
B.Scope statement
C.Network diagram
D.Work Breakdown Structure (WBS)
AnswerD

Correct: WBS is the output of decomposition.

Why this answer

Decomposition of scope results in a Work Breakdown Structure (WBS), which breaks down deliverables into work packages.

138
MCQeasy

A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?

A.High-level project objectives and constraints
B.Earned value metrics
C.Risk register with probability and impact matrix
D.Detailed work breakdown structure
AnswerA

The charter includes high-level objectives, constraints, and assumptions.

Why this answer

The project charter includes high-level scope, objectives, assumptions, and constraints, but detailed work packages are developed during planning.

139
MCQhard

During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?

A.Inform the change control board
B.Submit a change request
C.Update the project management plan
D.Deny the change
AnswerB

A formal change request initiates the change control process.

Why this answer

The first step in change control is to submit a change request, which then undergoes impact analysis.

140
MCQhard

A project has a budget at completion (BAC) of $200,000, earned value (EV) of $120,000, and actual cost (AC) of $130,000. What is the estimate at completion (EAC) if the cost performance is expected to continue?

A.$230,000
B.$210,000
C.$220,000
D.$216,667
AnswerD

EAC = BAC / CPI = 200000 / (120000/130000) ≈ 216,667.

Why this answer

If cost performance continues, EAC = BAC / CPI = BAC / (EV/AC) = 200000 / (120000/130000) = 200000 / 0.9231 ≈ $216,667.

141
MCQeasy

In a fixed-price contract, which party bears the risk of cost overruns?

A.Both equally
B.Seller
C.Buyer
D.Neither
AnswerB

The seller bears the risk of cost overruns.

Why this answer

In a fixed-price contract, the seller bears the risk of cost overruns because the price is fixed.

142
MCQmedium

During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?

A.Performing
B.Forming
C.Norming
D.Storming
AnswerC

Norming involves collaboration and open sharing of ideas.

Why this answer

In the norming stage, team members begin to work together and share ideas openly.

143
MCQhard

A project manager is calculating the Expected Monetary Value (EMV) for a risk event. The probability of the risk occurring is 20%, and the impact if it occurs is $50,000. What is the EMV?

A.$40,000
B.$10,000
C.$250,000
D.$100,000
AnswerB

Correct: 20% of $50,000 = $10,000.

Why this answer

EMV = Probability × Impact = 0.20 × $50,000 = $10,000. Positive EMV typically indicates an opportunity, but here it's a threat so negative.

144
MCQmedium

A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?

A.Bottom-up estimation
B.Three-point estimation
C.Parametric estimation
D.Analogous estimation
AnswerD

Analogous estimation uses historical data from similar projects.

Why this answer

Analogous estimation uses historical data from similar projects.

145
MCQeasy

A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?

A.High-level budget and schedule
B.Detailed risk response plan
C.Work Breakdown Structure
D.Communication management plan
AnswerA

The project charter contains high-level budget and schedule estimates.

Why this answer

The project charter formally authorizes the project and includes the project purpose, objectives, high-level scope, budget, schedule, assumptions, constraints, and the authority of the project manager. The other options are developed later in the planning or executing phases.

146
Multi-Selecthard

A project is in the Monitoring and Controlling phase. A change request has been submitted to add a new feature. The change control board (CCB) has approved the change. Which THREE actions should the project manager take next?

Select 3 answers
A.Close the project
B.Communicate the change to stakeholders
C.Update the project baselines (e.g., scope, schedule, cost)
D.Reject the change because it was not in the original plan
E.Implement the change as planned
AnswersB, C, E

Correct. Stakeholders need to be informed of approved changes.

Why this answer

After approval, the project manager must update the relevant project baselines (e.g., scope, schedule, cost), implement the change, and then monitor its effect. Communication is also key, but updating baselines and implementing are primary.

147
MCQmedium

A project team is estimating costs for a new software development project. They use data from a similar previous project and adjust for size differences. Which estimating technique is being used?

A.Parametric estimating
B.Bottom-up estimating
C.Three-point estimating
D.Analogous estimating
AnswerD

Analogous uses past similar projects as basis.

Why this answer

Analogous estimation uses historical data from similar projects, adjusted for differences.

148
Multi-Selectmedium

A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which TWO quadrants should the project manager apply the strategy of 'Manage Closely'?

Select 1 answer
A.Medium power, medium interest
B.High power, low interest
C.High power, high interest
D.Low power, low interest
E.Low power, high interest
AnswersC

Correct. These are key players who require close management.

Why this answer

The power/interest grid categorizes stakeholders by their power (ability to influence) and interest (concern about project outcomes). 'Manage Closely' applies to high-power, high-interest stakeholders (key players) who require active engagement.

149
Multi-Selectmedium

A project manager is identifying response strategies for a risk that could impact the project schedule. Which TWO options are risk response strategies? (Select TWO.)

Select 2 answers
A.Ignore
B.Enhance
C.Transfer
D.Escalate
E.Avoid
AnswersC, E

Transfer shifts risk to a third party.

Why this answer

Common risk response strategies include avoid, transfer, mitigate, and accept. Escalate and ignore are not standard strategies.

150
MCQeasy

Which cost estimation technique uses historical data from similar projects to estimate the current project?

A.Three-point
B.Bottom-up
C.Parametric
D.Analogous
AnswerD

Analogous uses similar project history.

Why this answer

Analogous estimation relies on historical data from similar projects.

← PreviousPage 2 of 3 · 165 questions totalNext →