A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
22 days
Original critical path duration = 5+10+5 = 20 days. Delaying B by 2 days adds 2 days to the critical path, so new duration = 22 days. Float of D doesn't affect critical path.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
21 days
Why it's wrong here
Incorrect addition.
- ✗
20 days
Why it's wrong here
The delay extends the critical path.
- ✓
22 days
Why this is correct
Correct: 20 + 2 = 22 days.
- ✗
23 days
Why it's wrong here
Incorrect.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.