A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

22 days

Original critical path duration = 5+10+5 = 20 days. Delaying B by 2 days adds 2 days to the critical path, so new duration = 22 days. Float of D doesn't affect critical path.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 21 days

    Why it's wrong here

    Incorrect addition.

  • 20 days

    Why it's wrong here

    The delay extends the critical path.

  • 22 days

    Why this is correct

    Correct: 20 + 2 = 22 days.

  • 23 days

    Why it's wrong here

    Incorrect.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.