A construction project is underway, and the project manager is using a Gantt chart to track progress. The project is divided into five phases: Foundation, Framing, Plumbing, Electrical, and Finishing. The project manager notices that the Framing phase is behind schedule because of a delayed material shipment. The Gantt chart shows that Framing has a predecessor of Foundation and a successor of Plumbing. The project manager updates the Gantt chart to reflect the delay. Which action should the project manager take next?
Correct. Recalculating critical path helps assess overall schedule impact.
Why this answer
Option C is correct because a delay in the critical path will affect the project completion date; recalculating the critical path is necessary. Option A is wrong because updating the timeline without assessing impact is incomplete. Option B is wrong because it ignores the schedule impact.
Option D is wrong because crashing should be considered after assessing the critical path.