976
MCQmedium

A project manager is using a quality tool that displays data points over time with upper and lower control limits. The tool helps distinguish between common cause and special cause variation. Which tool is this?

A.Scatter diagram
B.Pareto chart
C.Fishbone diagram
D.Control chart
AnswerD

Control charts display data over time with control limits.

Why this answer

A control chart plots data over time with control limits to identify variation types.

977
Multi-Selecteasy

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Select 2 answers
A.Create the project charter
B.Update the risk register
C.Archive project documents
D.Develop the project schedule
E.Obtain formal acceptance of deliverables from the sponsor
AnswersC, E

Correct. Archiving documents is part of closing.

Why this answer

Project closure includes formal acceptance from the sponsor/customer and archiving project documents. Releasing resources and lessons learned are also closure activities, but the question asks for TWO from the options.

978
MCQeasy

A project manager is identifying stakeholders and documenting their interests and influence. In which project life cycle phase is this activity performed?

A.Executing
B.Initiating
C.Closing
D.Planning
AnswerB

Identifying stakeholders is part of the Initiating phase.

Why this answer

Identifying stakeholders is a key activity in the Initiating phase, where the project is formally authorized and stakeholders are identified.

979
MCQmedium

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

A.Fixed-price
B.Time and Materials (T&M)
C.Cost-reimbursable
D.Cost-plus
AnswerA

Correct: fixed-price has a set price.

Why this answer

A fixed-price contract has a predetermined price that does not change based on the seller's cost performance.

980
Multi-Selecthard

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Select 3 answers
A.Ignore
B.Enhance
C.Avoid
D.Mitigate
E.Transfer
AnswersC, D, E

Correct: Avoid involves eliminating the risk.

Why this answer

The main risk response strategies are Avoid, Transfer, Mitigate, and Accept. Enhance is for opportunities, not threats.