CompTIA Project+ PK0-005 (PK0-005) — Questions 976984

984 questions total · 14pages · All types, answers revealed

Page 13

Page 14 of 14

976
MCQmedium

During the planning phase, a project manager conducts a stakeholder analysis. Which of the following is the primary purpose of this activity?

A.To identify potential risks that stakeholders might introduce
B.To assign team members to project tasks
C.To define the project scope and deliverables
D.To identify and categorize stakeholders based on their interest and influence
AnswerD

Primary purpose of stakeholder analysis.

Why this answer

Option A is correct because stakeholder analysis identifies stakeholders' interests, influence, and expectations to manage them effectively. Option B is incorrect because stakeholder analysis is not about identifying project risks directly. Option C is incorrect because it does not define project scope.

Option D is incorrect because it does not assign tasks.

977
Multi-Selectmedium

A project manager is selecting tools for agile project management. Which TWO tools are specifically designed for agile methodologies?

Select 2 answers
A.Smartsheet
B.Jira
C.Microsoft Project
D.Trello
E.Monday.com
AnswersB, D

Jira is built for agile teams.

Why this answer

Jira is widely used for agile project management, and Trello supports Kanban boards, a common agile tool. Microsoft Project is more traditional. Smartsheet and Monday.com are not specifically agile-only.

978
Multi-Selectmedium

Which TWO documents are typically found in a project's procurement management plan?

Select 2 answers
A.Risk register
B.Project charter
C.Work Breakdown Structure (WBS)
D.Request for Proposal (RFP)
E.Statement of Work (SOW)
AnswersD, E

RFP is used to solicit bids from vendors.

Why this answer

Procurement documents include SOW (Statement of Work) and RFP (Request for Proposal). The project charter and WBS are not procurement-specific; the risk register is a risk document.

979
MCQmedium

Which document defines the roles and responsibilities of stakeholders in a project and is often presented as a matrix?

A.RACI matrix
B.Communication plan
C.Stakeholder register
D.Project charter
AnswerA

Correct: RACI matrix assigns responsibility and accountability for tasks.

Why this answer

The RACI matrix (Responsible, Accountable, Consulted, Informed) is the correct document because it explicitly defines stakeholder roles and responsibilities in a project and is presented as a matrix format. This aligns with the PMBOK Guide and the PK0-005 exam objectives for Tools and Documentation, where the RACI matrix is the standard tool for clarifying participation levels across project tasks.

Exam trap

The trap here is that candidates often confuse the stakeholder register (a list) with the RACI matrix (a matrix of roles and responsibilities), leading them to select Option C instead of the correct matrix-based document.

How to eliminate wrong answers

Option B (Communication plan) is wrong because it defines how, when, and by whom project information is distributed, not the specific roles and responsibilities of stakeholders in a matrix format. Option C (Stakeholder register) is wrong because it is a list of stakeholders with basic identification and classification details, not a matrix that maps roles to tasks. Option D (Project charter) is wrong because it authorizes the project and assigns the project manager, but does not provide a detailed matrix of stakeholder roles and responsibilities across activities.

980
MCQmedium

A project manager is using a quality tool that displays data points over time with upper and lower control limits. The tool helps distinguish between common cause and special cause variation. Which tool is this?

A.Scatter diagram
B.Pareto chart
C.Fishbone diagram
D.Control chart
AnswerD

Control charts display data over time with control limits.

Why this answer

A control chart plots data over time with control limits to identify variation types.

981
Multi-Selecteasy

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Select 2 answers
A.Create the project charter
B.Update the risk register
C.Archive project documents
D.Develop the project schedule
E.Obtain formal acceptance of deliverables from the sponsor
AnswersC, E

Correct. Archiving documents is part of closing.

Why this answer

Project closure includes formal acceptance from the sponsor/customer and archiving project documents. Releasing resources and lessons learned are also closure activities, but the question asks for TWO from the options.

982
MCQeasy

A project manager is identifying stakeholders and documenting their interests and influence. In which project life cycle phase is this activity performed?

A.Executing
B.Initiating
C.Closing
D.Planning
AnswerB

Identifying stakeholders is part of the Initiating phase.

Why this answer

Identifying stakeholders is a key activity in the Initiating phase, where the project is formally authorized and stakeholders are identified.

983
MCQmedium

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

A.Fixed-price
B.Time and Materials (T&M)
C.Cost-reimbursable
D.Cost-plus
AnswerA

Correct: fixed-price has a set price.

Why this answer

A fixed-price contract has a predetermined price that does not change based on the seller's cost performance.

984
Multi-Selecthard

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Select 3 answers
A.Ignore
B.Enhance
C.Avoid
D.Mitigate
E.Transfer
AnswersC, D, E

Correct: Avoid involves eliminating the risk.

Why this answer

The main risk response strategies are Avoid, Transfer, Mitigate, and Accept. Enhance is for opportunities, not threats.

Page 13

Page 14 of 14