PK0-005 Practice Question: Match each document type to its description in…

Match each document type to its description in project management.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Authorizes the project and assigns the project manager

Comprehensive plan that guides execution and control

Lists identified risks, their analysis, and response plans

Documents and tracks project issues throughout the project

Records knowledge gained during the project for future use

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Charter: A document that formally authorizes the project and gives the project manager authority.

The correct matches are: Project Charter (authorization), Stakeholder Register (stakeholders), and Lessons Learned (knowledge). Common confusions involve swapping definitions of Project Management Plan and Risk Register.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Charter: A document that formally authorizes the project and gives the project manager authority.

    Why this is correct

    The project charter formally authorizes the project and assigns authority to the project manager.

  • Project Management Plan: A document that identifies risks and their response plans.

    Why it's wrong here

    Incorrect: This definition describes the Risk Register, not the Project Management Plan.

  • Risk Register: A document that defines how the project is executed, monitored, and controlled.

    Why it's wrong here

    Incorrect: This definition describes the Project Management Plan, not the Risk Register.

  • Stakeholder Register: A document that identifies stakeholders and their interests.

    Why this is correct

    The stakeholder register lists stakeholders and their relevant interests or influence.

  • Lessons Learned: A document that captures knowledge gained during the project.

    Why this is correct

    Lessons learned documents are used to capture and share knowledge for future projects.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.