A project manager is reviewing change requests. Which THREE types of changes would be subject to integrated change control?
Schedule changes shift the approved schedule baseline, so integrated change control is required to assess knock-on effects on scope, cost, resources and risk, then formally approve and update the schedule baseline and related project documents.
Why this answer
Integrated change control is the process of reviewing all change requests, approving changes, and managing changes to deliverables, project documents, and the project management plan. Option A (Schedule change) is correct because any modification to the project schedule baseline, such as shifting milestones or activity dates, must go through integrated change control to assess impacts on other knowledge areas. Option B (Scope change) is correct because changes to the project or product scope alter the scope baseline and require formal review and approval to prevent scope creep.
Option C (Cost change) is correct because adjustments to the cost baseline or budget require integrated change control to evaluate funding, reserves, and impacts on the business case. Option D (Office supply order) is not correct because routine procurement of administrative supplies is an operational activity, not a change to project baselines or the project management plan. Option E (Team member vacation request) is not correct because it is a routine resource/HR administrative matter handled through normal team management, not a formal change request affecting project baselines.
Exam trap
PK0-005 often tests the misconception that any project-related request is a change requiring ICC — candidates must distinguish baseline-affecting changes from routine operational or administrative requests.