Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: Based on the exhibit, which risk should the…

Network Topology
|Refer to the exhibit.Risk Register (Excerpt)

Based on the exhibit, which risk should the project manager address first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk R01 (Network outage)

The project manager should address Risk R01 (Network outage) first because it has the highest risk score (0.72), which is the product of its probability and impact. This indicates the highest priority for response. Option A is incorrect because highest probability alone does not determine priority without considering impact. Option B is incorrect because the type of response (mitigation) does not indicate priority level. Option C is incorrect because highest impact alone does not determine priority without considering probability.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk with highest probability (R01 or R04)

    Why it's wrong here

    Probability alone does not determine priority; risk score combines probability and impact.

  • Risk with a mitigation response (R01)

    Why it's wrong here

    Response type does not indicate priority; all risks need responses.

  • Risk with highest impact (R01 or R02)

    Why it's wrong here

    Impact alone does not determine priority; risk score combines probability and impact.

  • Risk R01 (Network outage)

    Why this is correct

    Highest risk score (0.72) requires immediate attention.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Refer to the exhibit. Which risk should the project manager address first?

medium
  • A.All risks have equal priority
  • B.R-002
  • C.R-001
  • D.R-003

Why C: R-001 has the highest risk score (0.75), indicating the highest priority. Higher scores require more immediate attention.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.