PRINCE2F People: organizations, teams, and leadership Practice Question

The Project Board is reviewing an Exception Report that recommends a change to the project's scope. Who on the Project Board is primarily responsible for deciding whether the change is justified?

⚠ Common exam trap

PeopleCert often tests the distinction between the Executive's accountability for the business case and the Senior User's responsibility for user benefits, leading candidates to mistakenly choose the Executive when the question specifically asks about justification from a user perspective.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior User

The Senior User is primarily responsible for defining the benefits and ensuring the project delivers a product that meets user needs. When an Exception Report recommends a scope change, the Senior User must assess whether the change is justified from a user-benefit perspective, as they represent the interests of those who will use the project's output. In PRINCE2, the Senior User's role includes approving changes that affect the project's scope, ensuring they align with the business case and user requirements.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Supplier

    Why it's wrong here

    The Senior Supplier provides supplier capabilities, not user justification.

  • Project Manager

    Why it's wrong here

    The Project Manager proposes but does not decide on scope changes.

  • Senior User

    Why this is correct

    The Senior User is responsible for representing user requirements and benefits.

  • Senior Responsible Owner (SRO/Executive)

    Why it's wrong here

    The SRO has overall accountability but the Senior User provides the user perspective on scope changes.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.