PRINCE2F PRINCE2 Processes Practice Question
What is the purpose of the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To decide whether to initiate the project
SU ensures that the project has a viable business case and necessary foundation before committing to full initiation. It checks if the project is worthwhile and doable.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To appoint the Project Board
Why it's wrong here
The Executive is appointed in SU, but the full Board is appointed later.
- ✓
To decide whether to initiate the project
Why this is correct
SU determines if there is sufficient justification and information to proceed to initiation.
- ✗
To produce the Project Initiation Documentation
Why it's wrong here
PID is created in Initiating a Project, not SU.
- ✗
To close the project
Why it's wrong here
Closing is done in Closing a Project.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.