PRINCE2F Issue Practice Question
Which THREE of the following are types of issue defined in PRINCE2?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Request for Change
PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. Therefore, options A, B, and D are correct. Option C is a risk, not an issue, and option E is effectively the same as option A but under a different name; PRINCE2 uses the term 'Request for Change' specifically, so 'Change request' is not a recognized issue type.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Request for Change
Why this is correct
An RFC is a formal proposal for a change.
- ✓
Problem/Concern
Why this is correct
A problem/concern is any other issue that needs management attention.
- ✗
Risk
Why it's wrong here
Risk is a separate practice, not an issue type.
- ✓
Off-specification
Why this is correct
An Off-spec is a failure to meet a specification.
- ✗
Change request
Why it's wrong here
The correct term is 'Request for Change'; 'Change request' is not the official PRINCE2 term.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.