Courseiva
PRINCE2 Practices →hardMultiple Select

PRINCE2F Issue Practice Question

Which THREE of the following are types of issue defined in PRINCE2?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Request for Change

In PRINCE2, issues are classified into three specific types: Request for Change (A), which proposes a modification to the baselined products or scope; Problem/Concern (B), which covers any other issue raised by a stakeholder that is not a change or an off-specification; and Off-specification (D), which describes a situation where a product will not meet its agreed requirements or specification. These three categories are explicitly defined in the PRINCE2 issue theme and are used to determine how each issue is managed through the issue and change control procedure. Risk (C) is incorrect because it is a separate PRINCE2 theme dealing with uncertainty, not a type of issue. Change request (E) is incorrect because it is a generic term and not one of the formal PRINCE2 issue types; the formal type is Request for Change.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Request for Change

    Why this is correct

    A Request for Change is one of PRINCE2's three defined issue types, alongside Off-Specification and Problem/Concern. It formally proposes an alteration to baselined products, such as the project plan or business case, satisfying the stem's requirement to identify recognised issue categories rather than general project risks or informal queries.

  • ✓

    Problem/Concern

    Why this is correct

    Problem/Concern is not one of PRINCE2's three defined issue types; those are Request for Change, Off-Specification, and Problem/Concern — wait, Problem/Concern is indeed the third. PRINCE2 defines issues as changes, off-specifications, or problems/concerns, so this option satisfies the stem's requirement for a recognised issue type.

  • ✗

    Risk

    Why it's wrong here

    Risk is a separate PRINCE2 theme with its own register and process, not one of the three issue types (request for change, off-specification, problem/concern). It is tempting because risks and issues are both logged and escalated, but risk management handles uncertainty, whereas issues cover problems already affecting the project.

  • ✓

    Off-specification

    Why this is correct

    Off-specification is one of PRINCE2's three issue types, alongside request for change and problem/concern. It records a product that will not meet its agreed specification, so the Project Manager can assess impact and decide on corrective action.

  • ✗

    Change request

    Why it's wrong here

    The correct term is 'Request for Change'; 'Change request' is not the official PRINCE2 term.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.