Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

A Project Manager receives a forecast that a Work Package will exceed its tolerance. What should the PM do?

⚠ Common exam trap

Candidates often confuse Work Package tolerance with stage tolerance, leading candidates to immediately escalate to the Project Board (Option C) when the correct first step is to discuss with the Team Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Discuss with the Team Manager to understand the situation and consider options

In PRINCE2, when a Work Package is forecast to exceed its tolerance, the Project Manager must first discuss with the Team Manager to understand the situation and explore options. This aligns with the 'manage by exception' principle, where the PM is responsible for managing within stage tolerances and only escalates to the Project Board if the stage tolerance itself is threatened. The PM must gather detailed information before deciding on corrective actions or escalation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Discuss with the Team Manager to understand the situation and consider options

    Why this is correct

    The PM should first understand the issue from the Team Manager.

  • Inform the Senior Supplier and request additional resources

    Why it's wrong here

    The PM should not bypass the Team Manager and go directly to the Senior Supplier.

  • Immediately raise an Exception Report to the Project Board

    Why it's wrong here

    The PM should first discuss with the Team Manager; escalation may not be needed if the issue is manageable.

  • Update the Stage Plan with the new forecast

    Why it's wrong here

    The PM cannot unilaterally change the plan if tolerance might be breached.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.