PRINCE2F People: organizations, teams, and leadership Practice Question

A Project Manager receives a forecast that a Work Package will exceed its tolerance. What should the PM do?

⚠ Common exam trap

Candidates often confuse Work Package tolerance with stage tolerance, leading candidates to immediately escalate to the Project Board (Option C) when the correct first step is to discuss with the Team Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Discuss with the Team Manager to understand the situation and consider options

In PRINCE2, when a Work Package is forecast to exceed its tolerance, the Project Manager must first discuss with the Team Manager to understand the situation and explore options. This aligns with the 'manage by exception' principle, where the PM is responsible for managing within stage tolerances and only escalates to the Project Board if the stage tolerance itself is threatened. The PM must gather detailed information before deciding on corrective actions or escalation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Discuss with the Team Manager to understand the situation and consider options

    Why this is correct

    Tolerance breaches are escalated, but the PM first works with the Team Manager to establish cause and evaluate corrective options. That discussion feeds an Exception Report to the Project Board, which decides; unilateral action exceeds the PM's authority.

  • ✗

    Inform the Senior Supplier and request additional resources

    Why it's wrong here

    Informing the Senior Supplier and requesting resources bypasses the agreed change and escalation routes; the PM should first take corrective action within delegated tolerance. It is tempting because suppliers provide resources, but PRINCE2 requires the PM to manage the Work Package within tolerance before escalating.

  • ✗

    Immediately raise an Exception Report to the Project Board

    Why it's wrong here

    A forecast breach of Work Package tolerance is first handled by the PM taking corrective action within stage tolerance; escalation to the Project Board occurs only if stage-level tolerance is threatened. It is tempting because Exception Reports address tolerance breaches, but they apply at stage or project level, not Work Package level.

  • ✗

    Update the Stage Plan with the new forecast

    Why it's wrong here

    Updating the Stage Plan alone does not address the forecast breach; the PM must first attempt corrective action, and if stage tolerance is threatened, escalate. It is tempting because plans are revised when forecasts change, but recording the variance does not resolve the tolerance issue.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.