PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorize Work Packages
During CS, the PM authorizes Work Packages and reviews the Business Case (if needed). Producing Highlight Reports is also a CS activity, but the question asks for two; authorizing Work Packages and reviewing the Business Case are both correct. Producing the End Stage Report is from SB.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Produce the End Stage Report
Why it's wrong here
Done in SB.
- ✓
Authorize Work Packages
Why this is correct
Done in CS.
- ✓
Review the Business Case for continued viability
Why this is correct
The PM reviews the Business Case during CS.
- ✗
Produce the Lessons Report
Why it's wrong here
Done in CP.
- ✗
Authorize project closure
Why it's wrong here
Done by the Board in DP.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.