PRINCE2F People: organizations, teams, and leadership Practice Question
During the Initiating a Project process, which document is created that defines how the project will be controlled?
⚠ Common exam trap
Test-takers frequently confuse the Project Brief (a high-level outline created in Starting Up a Project) with the PID (the detailed control document created in Initiating a Project), as both contain similar elements but serve different purposes and are created at different process stages.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Initiation Documentation (PID)
The Project Initiation Documentation (PID) is the key document created during the Initiating a Project process that defines how the project will be controlled. It consolidates the project's scope, objectives, and controls, including the management stages, tolerances, and reporting arrangements, providing a baseline for decision-making and governance throughout the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Business Case
Why it's wrong here
The Business Case justifies the project's viability and benefits; it does not define the controls, tolerances, or reporting arrangements. It is tempting because it is created during Initiating a Project, but the Project Initiation Documentation, specifically the controls strategy, covers control.
- ✗
Project Brief
Why it's wrong here
The Project Brief is a pre-project document produced during Starting up a Project; it outlines the mandate and scope, not the controls. The Project Initiation Documentation contains the project controls baseline, so the Brief fails this scenario. It would be the right artefact earlier, before the project board authorises initiation.
- ✗
Stage Plan
Why it's wrong here
A Stage Plan covers one management stage's activities, products, and tolerances, not project-wide control arrangements. It is tempting because plans do specify controls, but the Project Initiation Documentation defines how the entire project will be directed and controlled.
- ✓
Project Initiation Documentation (PID)
Why this is correct
The Project Initiation Documentation assembles the project definition, business case, plans and controls, and is the baseline against which the Project Board authorises and subsequently directs the project, satisfying the need for a single controlling document.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.