PRINCE2F People: organizations, teams, and leadership Practice Question
According to PRINCE2, which role is responsible for defining the project's tolerances?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Project Board defines project-level tolerances; the Project Manager sets stage-level tolerances within them.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
Team Managers work within tolerances.
- ✗
Senior User
Why it's wrong here
The Senior User is part of the Board.
- ✗
Project Manager
Why it's wrong here
The PM proposes but the Board approves.
- ✓
Project Board
Why this is correct
The Board sets project-level tolerances.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.