Which TWO of the following are types of issues in PRINCE2?

⚠ Common exam trap

A common pitfall in PRINCE2 is confusing issue types with risk categories. 'Change' is not a formal issue type; the correct term is 'Request for Change'. Similarly, 'Opportunity' is a risk type, not an issue type. Know the three defined issue types: Request for Change, Off-specification, and Problem/Concern.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Request for Change

In PRINCE2, an issue is a relevant event that has occurred and requires management attention. A Request for Change (A) is a formal proposal for a modification to a product, baseline, or agreed scope, making it a standard type of issue. An Off-specification (D) is a type of issue that identifies a product that should be provided but is not, or that is provided but does not meet its specification, also making it a standard type of issue.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Request for Change

    Why this is correct

    An RFC is a type of issue.

  • ✗

    Change

    Why it's wrong here

    Change is a practice, not an issue type.

  • ✗

    Risk

    Why it's wrong here

    A risk is an uncertain event, not an issue.

  • ✓

    Off-specification

    Why this is correct

    An Off-spec is a type of issue.

  • ✗

    Opportunity

    Why it's wrong here

    In PRINCE2, the three defined types of issues are a Request for Change, an Off-Specification, and a Problem/Concern. An Opportunity is not a recognised issue type; it is instead a type of risk (a positive risk) managed via the risk management approach. This option is tempting because the term "opportunity" sounds like a project event requiring a decision, but PRINCE2 explicitly separates risk management from issue management, reserving "issue" for events that have already occurred or require a deviation decision.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.