PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

In the Closing a Project process, what is the Project Board's responsibility?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To confirm the project has met its objectives and authorize closure

The Project Board authorizes the closure of the project after reviewing the End Project Report and Lessons Report, ensuring all products are accepted and benefits review plans are in place.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To produce the Lessons Report

    Why it's wrong here

    The Project Manager produces the Lessons Report; the Project Board reviews and authorizes closure.

  • To hand over the project products to the operational environment

    Why it's wrong here

    Handover is done by the Project Manager or team; the Project Board authorizes the handover.

  • To confirm the project has met its objectives and authorize closure

    Why this is correct

    In CP, the Project Board reviews the End Project Report and formally authorizes project closure.

  • To release the project resources

    Why it's wrong here

    Resource release is a project management activity; the Project Board authorizes closure, which triggers resource release.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. The Project Board is considering a request to close a project early due to loss of business justification. Which process is the Project Board using to make this decision?

medium
  • A.Managing a Stage Boundary
  • B.Closing a Project
  • C.Starting Up a Project
  • D.Directing a Project

Why D: The Project Board uses the Directing a Project process throughout the project, including authorising closure. Closing a Project is the process that produces the recommendation, but the decision to close is taken by the Project Board via Directing a Project.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.