A Work Package has been completed and the products have passed quality checks. What should the Team Manager do next in the Managing Product Delivery process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Deliver the Work Package to the Project Manager
The final activity in MP is to 'Deliver a Work Package', which involves handing over the completed products to the Project Manager and obtaining formal acceptance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Raise an Exception Report
Why it's wrong here
Exception Reports are for tolerance breaches, not for normal completion.
- ✗
Update the Project Plan
Why it's wrong here
The Project Plan is updated by the PM, not the Team Manager.
- ✗
Close the project stage
Why it's wrong here
Closing a stage is done by the PM in Managing a Stage Boundary.
- ✓
Deliver the Work Package to the Project Manager
Why this is correct
After completion, the Team Manager delivers the Work Package and obtains acceptance.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.